UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555
., 'r:211j'j 9,
JAN 5 1970 Docket Nos:
50-413 50-414 MEMORANDUM.FOR:
Steven A. Varga, Chief, Light Water'teactors Branch No. 4, DPM FROM:
Harley Silver, Project Manager, Light Water Reactors Branch No.
4, DPM
SUBJECT:
FORTHCOMING VISIT TO CATAWBA NUCLEAR STATION Date 6 Time:
January 24 and 25, 1979 S:00 a.m.
Location:
Catawba Nuclear Station
Purpose:
NRC Forecast Panel Fuel Load Date Assessment (See attached agenda)
\\
Participants:
Duke Power Comoany As required NRC H. Silver W.
Lovelace S. Kari C. McFarland J< /azk._ lver, Project Ma
/
{,
arley Light later Reactors Branch No. 4 Divis on of Project Management
Enclosure:
As stated cc:
See next page follZo W t d
Duke Power Company ccs:
William H. Grigg, Esq.
Duke Power Company P. O. Box 33189 Charlotte, North Carolina 28242 William L. Porter, Esq.
Duke Power Company P. O. Box 33189 Charlotte, North Carolina 28242 J. Michael McGarry III, Esq.
Debevoi'e & Liberman 700 S. lore. am Building 1
806 ISth Street, NW Washington, D. C.
20006 Mr. Jesse L. Riley, President Carolina Environmental Study Group 854 Henley Place Charlotte, North Carolina 23208 M. Richbourg Roberson, Esq.
Staff Attorney Attorney General's Office P. O. Box 11549 Columbia, South Carolina 29211 Walton J. McLeod, Jr., Esq.
General Counsel South Carolina State Board of Health J. Marion Sims Building 2600 Bull Street Columbia, South Carolina 29201 James W. Burch, Director Nuclear Advisory Counsel 2600 Bull Street Columbia, South Carolina 29201
TENATIVE AGENDA JAN 5
'970 NRC SITE VISIT TO CATAWBA NUCLEAR STATION January 24 - 25, 1979 General Purpose of Visit -
Discussion of overall project status, observation of construction activities in progress and detailed discussion of project schedule to enable the NRC Forecast Panel to confirm the scheduled fuel load date for Units 1 and 2.
1st day NRC Presentation on Scope of Forecast and Purpose of Visit.
Licensee overview of plant project.
A.
Utility commitments on power.
B.
Overview of construction management organization (s) and activities.
C.
Project schedule (major milestones),
including schedule for licensing.
D.
Anticipated weather, financial problems, etc.
E.
Actual and Proposed Work Force -
Productivity.
F.
Material Quantities - total and presently completed.
Detailed discussion on engineering and design efforts.
LUNCH BREAK Tour of plant site and observation of construction activities.
Brief discussion on construction activities / problems / installation rates of various material quantities.
A.
Civil / Structural B.
Electrical
9 e
~
JAN 5 1979 C.
Piping 9
D. Mechanical E. Instrumentation and Air 2nd day Detailed discussion on procurement activities.
Detailed discussion with scheduling staff.
Discussion with plant operational staf f and review of pre-op testing plans.
NRC Presentation of Summary and Conclusions.
MEETING NOTIG DISIRIBUTION JAN 5 1979 Docket File J. Knight NRC PDR D. Ross Local PDR R. Tedesco TIC S. Pawlicki LhR #4 File Chief, SEB NPR Reading K. Kniel H. Denton W. Haass E. Case T. Novak D. Cmtchfield Z. Ros: toc:y D. Bunch R. Bosnak R. Boyd Chief, ICSB D. Vassallo W. Butler D. Skovholt F. Rosa W. Ga=till V. Moore F. Williams R. Vollmer J. Stol:
M. Ernst R. Baer R. Denise
- 0. Parr R. Ballard S. Varga B. Youngblood R. Clark W. Regan T. Speis G. Chipman P. Collins J. Collins C. Heltemes W. Kreger R. Houston G. Lear R. Mattson M. Spangler R. DeYoung V. Benaraya D. Muller J. Stepp ACRS (16)
L. Hulman L. Crocker H. Ornstein H. Berkcw L. Dreher Project Manager:
H. Silver B. Faulkenberry Attorney, ELD
Participants:
W.
Lovelace IE (3)
S. Kari SD (7)
C. McFarland M. Service Receptionist L. Rubenstein
@