Responds to NRC Re Violation Noted in IE Insp. Corrective Actions:Second Criticality Monitor Reinstalled After Maint & Calibr of Seven Connections to Alarms Completed
ML19282B648
Person / Time
Site: 07000152
Issue date: 02/19/1979
From: Ziemer P
PURDUE UNIV., WEST LAFAYETTE, IN
To: Davis A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML19282B647 List:
References
NUDOCS 7903160074
Download: ML19282B648 (1)


Text

.

PURDUE U N IV 5 R S ITY O P PIC E OF NEALTN PH Y SIC S AND R A D 90 L O GIC A L CONTROL SICMUCLEONICS DEPARTMENT WEST L A F AY ETTE, INDI AN A 4 7,07 February 19, 1979 A. B. Davis, Chief Fuel Facility and Materials Safety Branch U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137

Reference:

Docket No.70-152

Dear Mr. Davis:

This letter is in reply to your correspondence of February 15, 1979 concerning the " Notice of Violation" for activities authorized under Special Nuclear Materials License No. SNM-142. In response to the specified " Notice of Violation" we submit the following informa-tion on corrective action taken:

1.

The second criticality monitor for the FBBF was reinstalled after maintenance on Wednesday, January 31, 1979.

Calibration and connections to the alann systents were completed on February 3, 1979. All alarms and interfacing to the ventila-tion system and FBBF controls were tested and found to be operational.

2.

In the future, ir one of the alarm systems becomes inoperative, immediate steps will be taken to repair or replace it promptly.

3.

Full compliance with license condition 12 was achieved on February 3, 1979.

If additional information is required, please let me know.

,,}

Sincerely, fg f eg Paul L. Zi

,e r Radiological Control Officer cc: Frank M. Clikeman, Nuclear Engineering Robert R. Landolt, Radiological Control PLZ:dd 7003160074