ML19282B590
| ML19282B590 | |
| Person / Time | |
|---|---|
| Site: | Davis Besse |
| Issue date: | 02/07/1979 |
| From: | Fiorelli G NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | Jeffery Grant TOLEDO EDISON CO. |
| Shared Package | |
| ML19282B591 | List: |
| References | |
| NUDOCS 7903150428 | |
| Download: ML19282B590 (2) | |
See also: IR 05000346/1978030
Text
{{#Wiki_filter:~ 4
d 4 UNITED ST AT E S c h ,/ ,1 NUCLE AR REGULATORY COMMISSION , I, . { ' j REGloN lli
- i
f f 799 R OOSE V E L T R O /,D $'s . . . .e, f G L E N E L L Y N. iL LINOIS 60137 .# FEB 7 379 Docket No. 50-346 Toledo Edison Company ATTN: Mr. James S. Grant Vice President - Energy Supply Edison Plaza 300 bbdison Avenue Toledo, OH 43652 Gentlemen: This refers to the inspection conducted by Messrs. J. F. Streeter, J. 5. Creswell and J. D. Smith of this office on October 31 - November 2, December 20-22, 1978, and January 12-15, 1979, of activ- ities at Davis-Besse Nuclear Power Station, Unit 1, authorized by NRC Operating License No. NPF-3 and to the discussion of our findings with Mr. T. Murray at the conclusion of the inspection- The enclosed copy of our inspection report identifies areas examined during the inspection. Within these areas, the inspection consisted of a selective examination of procedures and representative records, observations, and interviews with personnel. No items of noncompliance with NRC requirements were identified during the course of this inspection. In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulation 5, a copy of this letter and the enclosed inspection report w'.ll be placed in the NRC's Public Document Room, except as follows. If this report contains information that you or your contractors believe to be proprietary, you must apply in writing to this office, within twenty days of your receipt of this letter, to withhold such information from public disclosure. The application must include a full statement of the reasons for which the information is con- sidered proprietary, and should be prepared so that proprietary information identified in the application is contained in an enclosure to the application. 790815 0cl2F6
. - . Toledo Edison Company -2- [[O 7 .J79 We will gladly discuss any questions you have concerning this inspection. Sincerely, ( , - Mgd# L Gaston Fiorelli, Chief Reactor Operations and Nuclear Support Branch Enclosure: IE Inspection Report No. 50-346/78-30 cc w/ encl: Mr. T. D. Murray, Station Superintendent Central Files Reproduction Unit NRC 20b PDR Local PDR NSIC TIC U. Young Park, Power Siting Concission }}