NRR E-mail Capture - FitzPatrick Emergency Amendment Public Conference Call Discussion Topics
ML19277D192
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 10/03/2019
From: Samson Lee
Plant Licensing Branch 1
To: Williams C
Exelon Generation Co
References
Download: ML19277D192 (2)


Text

1 NRR-DRMAPEm Resource From:

Lee, Samson Sent:

Thursday, October 3, 2019 12:42 PM To:

Williams, Christian D:(Exelon Nuclear)

Subject:

FitzPatrick Emergency amendment public conference call discussion topics Some discussion topics for public conference call:

  • EICB will need to know the date of the last successful completion of Tech Spec Required Surveillance SR 3.3.5.1.3 (for ISP-6A) (Channel Calibration), and the next due date for the surveillance, and the end date of the 25% grace period. [Tech Spec Table 3.3.5.1-1, Functions 4.3 and 5.e]
  • EICB will also need to know the date of the last successful completion of Tech Spec Surveillance Requirement 3.3.5.1.6, Functions 3.f and 3.g [Perform Logic System Functional Test], the next due date for the surveillance, and the end date of the 24% grace period.
  • What does it mean, exactly:

o The A and B Emergency Diesel Generators and their associated cooling water pumps and power supplies will be protected.

o The 4160V emergency buses will be protected.

o HPCI and RCIC will be protected.

o Both trains of RHR and CSP will be protected.

1. For the SRs to verify that valves are in the correct position, explain why they cannot be performed.
2. TS page 3.5.1-5 is blank. Is something missing? (Maybe SRs 3.5.1.7 and 3.5.1.8)
3. SR 3.5.1.9 - Discuss whether or not the pump has degraded in past tests.
4. SR 3.6.1.3.5 - Discuss whether or not there have been past failures for this SR.
5. SR 3.6.1.9.2 - Discuss if there has been any pump degradation seen in past inservice tests.
6. SR 3.6.2.3.2 - Discuss if there has been any pump degradation seen in past inservice tests.
7. SR 3.8.1.2 and SR 3.8.1.3 - Discuss whether or not there have been any recent failures.
8. SR 3.8.1.6 - Discuss whether or not there have been any recent failures.
9. SRs 3.8.1.4, 3.8.3.1, 3.8.3.2, 3.8.3.4 - Explain why these SRs have to be delayed.

Compensatory measures should be in a separate attachment for ease of reference.

Thanks, Sam

Hearing Identifier:

NRR_DRMA Email Number:

236 Mail Envelope Properties (BL0PR0901MB31853DCD38A2079E8EDE86779A9F0)

Subject:

FitzPatrick Emergency amendment public conference call discussion topics Sent Date:

10/3/2019 12:41:44 PM Received Date:

10/3/2019 12:41:00 PM From:

Lee, Samson Created By:

Samson.Lee@nrc.gov Recipients:

"Williams, Christian D:(Exelon Nuclear)" <Christian.Williams@exeloncorp.com>

Tracking Status: None Post Office:

BL0PR0901MB3185.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 1828 10/3/2019 12:41:00 PM Options Priority:

Standard Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Recipients Received: