Forwards Request for Addl Info to Complete Review of Sections 13.2 & 13.5 of PSAR Through Amend 14
ML19276G573
Person / Time
Site: 05000452, 05000453
Issue date: 05/16/1979
From: Collins P
Office of Nuclear Reactor Regulation
To: Stolz J
Office of Nuclear Reactor Regulation
References
NUDOCS 7907100685
Download: ML19276G573 (3)


Text

~~

-L r

sp

'd, UNITED STATES

[q,h) "

4 NUCLEAR REGULATOP.Y COMMisslON

+

. f.

WASHINGTON, D. C. 20555

/

MAY 161979

.g t

v l

y t

Docket Nos. 50-452/453

~"

MEMORANDUM FOR: John F. Stolz, Chief, Light Water Reactors Branch

' ' ~

No.1, Division of Project Management FROM:

Paul F. Collins, Chief, Operator Licensing Branch Division of Project Management

SUBJECT:

GREENWOOD ENERGY CENTER, UNITS 2 & 3, ACCEPTANCE REVIEW LICENSING STAGE: CP

=

BRANCH AND PROJECT MANAGER REQUESTING ASSISTANCE:

LWR-1, L. B. Engle I

REVIEW BRANCH INVOLVED: DPM:0LB l

REOUESTED COMPLETION DATE: May 15, 1979

=

We have reviewed Section 13.2 and 13.5 of the PSAR through Amendment 14.

-[.$

Based on our review, we have determined that the additional infomation i

indicated in Attachment A, is necessary for us to complete our review.

=

There may be additional changes to the Operator Licensing Guide that Z

will require revisions to your program during our next review. We will

'~

be available to discuss these items, should the appli ant desire.

.. si c

jd

^}:

Paul F. Collins, Chief

=6ff

==

Operator Licensing Branch Division of Project Management ggif

Enclosure:

Attachment A l

cc: w/ enclosure D. J. Skovholt

+

W. P. Haass D. B. Vassallo

=

L. B. Engle N. Haller

Enclosure A Greenwood Energy Center

=

Docket Nos. 50-452/453 r

441.1 It is highly desirable that experienced individuals

( 13. 2.1.1. 3) participate in courses utilizing a nuclear plant simulator similar to the facility for which the indiv-idual will be seeking a license. The applicant should provide this training for all candidates for an SR0 or R0 license using an NRC approved program.

Resolve this apparent discrepancy and provide the commitment that all license candidates attend such a training course.

=...

441.2 The applicant should provide a comnitment to conduct

((L

( 13. 2. 5.1)

~~

an initial fire protection training program, including:

..y

}

a.

Periodic drills during construction.

b.

Provisions for indoctrination of construction

{:

+

personnel, as necessary.

The initial training shall be completed prior to receipt of fuel at the site.

N 441.3 The applicant should provide a detailed description of the (13.2.5.2) t~ raining program for the individual (s) rescensible for the formulation and assurance of the imolementation of the fire protection program.

The training program shcuid address those items listed in Secticn A.1 of Accendix A

to Branth Technical Position ASB 9.5-1, Guidelines for Fire Protection for Nuclear Power Plants.

442.1 The applicant should commit to the conduct of all (13.5) safety-related operations by detailed written and j

\\

approved procedures.

442.2 The applicant should commit to provide written and (13.5) approved fire protection procedures and include them on the preliminary schedule for completion.

==

es I

i f

_-