Estimates That Radiological Effluent Tech Specs Will Be Completed by 790531 Instead of Original Date of 790330.Delay Caused by Need for Attention to Other NRC Requirements, Particularly Systematic Evaluation Program
ML19276F582
Person / Time
Site: San Onofre 
Issue date: 03/30/1979
From: Haynes J
SOUTHERN CALIFORNIA EDISON CO.
To: Ziemann D
Office of Nuclear Reactor Regulation
References
NUDOCS 7904060246
Download: ML19276F582 (1)


Text

_ - -...

F=

Southern California Edison Company W"

P. 7 Box 800 2244 W ALNUT GROVE Avf NUE ROSEME AD. C ALIFORNI A 91770 March 30, 1979 Director of Nuclear Reactor Regulation Attention:

Mr. D. L. Ziemann, Chief Operating Reactors Branch #2 Division of Operating Reactors U. S. Nuclear Regulatory Commission Washington, D.C.

20555 Geratlemen :

Subject:

Docket No. 50-206 Appendix I Technical Specifications San Onofre Nuclear Generating Station Unit 1 By letter dated January 12, 1979 we informed you that the radiological effluent technical specifications complying with 10CFR50 Appendix I would be available for submittal by March 30, 1979 The completion of these technical specifications has been delayed due to providing the necessary support to other NRC requirements, in particular the Systematic Evaluation Program.

We now estimate that the technical specifications will be completed and forwarded to you by May 31, 1979 If you have any questions concerning this, please let me know.

Very truly yours.

ayain J. G. Haynes Chief of Nuclear Engineering 5i9 79040602 %

..