Forwards IE Insp Repts 50-566/79-02 & 50-567/79-02 on 790123-26.No Noncompliance Noted
ML19276F216
Person / Time
Site: Yellow Creek  Tennessee Valley Authority icon.png
Issue date: 02/16/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML19276F217 List:
References
NUDOCS 7903280063
Download: ML19276F216 (2)


See also: IR 05000566/1979002

Text

e

UNITED ST ATES

g8 R800g'o

NUCLEAR REGULATORY COMMISSION

O'

o

g

g

$7

REGION il

{

g

.-

-.E

101 M ARIETTA STREET, N.W.

ATLANTA, CEORGI A 30303

%*****/

FEB 161979

In Reply Refer Tc:

RII:WBS

50-566/79-02

50-567/79-02

Tennessee Valley Authority

Attn:

Mr. H. G. Parris

Manager of Power

500A Chestnut Street Tower II

Chattanooga, Tennessee

37401

Gentlemen:

This refers to the inspection conducted by Mr. W. B. Swan of this office on

January 23-26, 1979, of activities authorized by NRC Construction Permit Not.

CPPR-172 and CPPR-173 for the Yellow Creek Nuclear Plant, Units 1 and 2

f acility, and to the discussion of our findings held with Mr. M. M. Price at

the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews

with personnel, and observations by the inspector.

We have examined actions you have taker. with regard to previously reported

unresolved items. The status of these items is discussed in the enclosed

report.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe to be

proprietary, it is necessary that you make a written application within

20 days to this office to withhold such information from public disclosure.

Any such application must include a full statement of the reasons on the

basis of which it is claimed that the information is proprietary, and should

be prepared so that proprietary information identified in the application is

contained in a separate part of the document.

If we do not hear from you in

this regard within the specified period, the report will be placed in the

Public Document Room.

.

790328 0 0 63

fEB 161979

.

.

Tennessee Valley Authority

-2-

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Sincerely,

[

[2

Charles E. Murph , Chief

Reactor Construction and Engineering

Support Branch

Enclosure:

Inspection Report No. 50-566/79-02,

and 50-567/79-02

cc w/ encl:

Mr. J. F. Cox

400 Commerce Street

W10Cl31 C

Knoxville, Tennessee

37902

Mr. M. M. Price, Project Manager

Yellow Creek Nuclear Plant

P. O. Box 2000

Iuka, Mississippi