Forwards IE Insp Repts 50-266/78-24 & 50-301/78-25 on 781211-15.No Noncompliance Noted
ML19274D766
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 01/12/1979
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Burstein S
WISCONSIN ELECTRIC POWER CO.
Shared Package
ML19274D767 List:
References
NUDOCS 7902260101
Download: ML19274D766 (2)


See also: IR 05000266/1978024

Text

e

d

4,

UNIT E D ST ATES

c

f

.1

NUC LE AR REGULATORY COMMISSION

f ',!

.

f

l'i

REGloNlif

  • .

f

799 ROoSE V E LT R Ct.D

$'5

J

y

'

G LE N E LLY tJ. ILLINOlb LL137

e.

=...*

J A N 1 '-

m

!?

[

Docket No. 50-26hf

Docket No. 50-301

"

Wisconsin Electric Power Company

ATIN:

Mr. Sol Burstein

Executive Vice President

Power Plants

231 West Michigan

Milwaukee, WI 53201

Gentlemen:

This refers to the inspection conducted by Mr. N. C. Choules of

this office on December 11-15, 1978, of activities at Point Beach

Nuclear Plant, Units 1 and 2, authorized by NRC Operating Licenses

No. DPR-24 and No. DPR-27 and to the discussion of our findings

with Mr. Reed and others of your staff at the conclusion of the

inspection.

The enclosed copy of our inspection report identifies areas

examined during the inspection. Within these areas, the

inspection consisted of a selective examination of procedures

and representativc records, observations, and interviews with

personnel.

No items of noncompliance with KRC requirements were identified

during the course of this inspection.

In accordance with Section 2.790 of the NRC's " Rules of

Practice," Part 2, Title 10, Code of Federal Regulations, a

copy of this letter and the enclosed inspection report will

be placed in the NRC's Public Document Room, except as follows.

If this report contains information that you or your contractors

believe to be proprietary, you must apply in writing to this

office, within twenty days of your receipt of this letter, to

withhold such information from public disclosure.

The

application must include a full statement of the reasons for

which the information is considered proprietary, and should be

prepared so that proprietary information identified in the

application is contained in an enclosure to the application.

7 9 0 2 26 0 lot

.

.

i "'

Wisconsin Electric Power

-2-

'

Company

We will gladly discuss any questions you have cencerning this

inspection.

..

re-

.-

47

Sincerely,

c

{~),

UE

cGaston Fiorelli,

hief

I Reactor Operations and

Nuclear Support Bianch

Enclosure:

lE Inspection

Rpts No. 50-266/78-24

and No. 50-301/78-25

cc w/ encl:

Mr. G. A. Reed, Manager

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC