DUKE POWER COMPANY WILLIA'i B. MCGUIRE NUCLEAR STATION, UNITS 1 AND 2 OOCKET NOS. 50-369 AND 50-370 ORDER EXTENDING CONSTRUCTION COMPLETION DATES Duke Power Ccmpany is the holder of Construction Permit Nos. CPPR-83 and CPPR-84 issued by the Atomic Energy Commission
- on F.Lruary 28, 1973, for construction of the William B. McGuire Nuclear Station, Units 1 and 2 presently under construction at the Company's site on the shore of Lake Norman in Mecklenburg County, North Carolina.
In response to previous requests from Duke Power Company (the applicant), the Nuclear Regulatory Commission issued an Order on August 3, 1976 extending the latest date for completion of construction to August 1, 1978 for Unit I and August 1,1979 for Unit 2.
By letter dated June 29, 1978, the applicant filed a request for a second extension of the completion dates, and supplemented its request by submitting additional information on November 7, 1978. This extension was requested because construction has been delayed due to, among other things, pipe hanger problems, system changes, 6nd preoperational testing.
This action involves no significant hazards consideration; good cause has been shown for the delay; and the requested extension is for a reasonable period, the bases for which are set forth in a staff evaluation, dated December 26, 1978.
- Ef fecti ve January 20, 1975, the Atomic Energy Commission became the Nuclear Regulatory Commission and Permits in effect an that day were continued under the authority of the Nuclear Regulatory Commission.
7 9 010 5 0?lG)I
. The preparation of an environmental impact statement for this particular action is not warranted because there will be no environmental impact attributable to the action authorized by the Order other than that which has already been predicted and described in the Comission's Final Environmental Statement - Operating License Stage for the McGuire f acility, published in April 1976 and the Final Environmental Statement - Construction Permit Stage published in October 1972. A Negative Declaration and an Environmental Impact Appraisal have been prepared and are available, as are the above stated documents, for public inspection at the Commission's Public Document Room, 1717 H Street, N.
W., Washington, D. C. 20555 and at the local public document room established for McGuire at the Public Library of Charlotte and Mecklenburg County, 310 North Tryon Street, Charlctte, North Carolina 28202.
IT IS HEREBY ORDERED THAT THE latest completion dates are extended for CPPR-83 from August 1,1978 to April 30, 1979 and for CPPR-84 from August 1, 1979 to December 31, 1980.
FOR THE NUCLEAR REGULATORY COMMISSION f
Roger S.
oyd, Directo Division of Project Management; Office of Nuclear Reactor Regulation Date of Issuance: December 26, 1978
-