UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 October 1, 2019 Mr. Bryan Hanson Senior Vice President, Exelon Generation President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

TERMINATION OF REACTOR OVERSIGHT PROCESS FOR THREE MILE ISLAND NUCLEAR STATION, UNIT 1 AND COMMENCEMENT OF DECOMMISSIONING INSPECTION PROGRAM

Dear Mr. Hanson:

This letter is to inform you that oversight activities by the U.S. Nuclear Regulatory Commission (NRC) at the Three Mile Island Nuclear Station (TMI), Unit 1 will no longer be performed in accordance with our operating power reactor inspection program. The NRCs oversight of your future activities at TMI Unit 1 will be conducted in accordance with our decommissioning power reactor inspection program and will be led by our Region I Division of Nuclear Materials Safety (DNMS).

On June 20, 2017, Exelon Generation Company, LLC (Exelon) notified the NRC of its intent to permanently shut down TMI Unit 1 (ADAMS Accession Number: ML17171A151). On September 26, 2019, Exelon certified cessation of power operations and the permanent removal of fuel from the TMI Unit 1 reactor vessel (ADAMS Accession Number: ML19269E480). The NRC will no longer use Inspection Manual Chapter (IMC) 0305, Operating Reactor Assessment Program, IMC 0608, Performance Indicator Program, and IMC 2515, Light-Water Reactor Inspection Program when conducting oversight activities and assessing site performance.

Therefore, it is also no longer necessary to report Reactor Oversight Process performance indicator data for TMI Unit 1. The results of inspection activities completed under IMC 2515 will be provided in future correspondence. Although the inspection program for NRC oversight at your facility has changed, all license commitments remain in effect until altered by formal action from the NRC.

The NRCs oversight of your licensed activities as you progress through decommissioning will be conducted under the provisions in IMC 2561, Decommissioning Power Reactor Inspection Program. The objectives of the decommissioning inspection program are to verify that decommissioning activities are being conducted safely, that spent fuel is safely being stored, and that site operations and license termination activities are in conformance with applicable regulatory requirements, licensee commitments, and management controls.

As defined in IMC 2561, TMI Unit 1 is currently in the Post-Operation Transition Phase of decommissioning and the inspections as listed in IMC 2561, Appendix A, Core Inspection Procedures for that phase will be conducted at TMI Unit 1. In addition, the inspection

B. Hanson 2 procedures listed in IMC 2561, Appendix B, Discretionary Procedures for Decommissioning Power Reactors could be performed based on site activities and conditions.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records component of the NRCs Agencywide Documents Access and Management System (ADAMS).

ADAMS is accessible from the NRC wesite at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (610) 337-6953 or Steve Hammann, Senior Health Physicist, at (610) 337-5399 with any questions you may have regarding this letter.

Sincerely,

/RA/

Anthony Dimitriadis, Chief Decommissioning, ISFSI, and Reactor HP Branch Division of Nuclear Materials Safety Docket No: 50-289 License No: DPR-50 cc: Distribution via ListServ

B. Hanson 2 procedures listed in IMC 2561, Appendix B, Discretionary Procedures for Decommissioning Power Reactors could be performed based on site activities and conditions.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records component of the NRCs Agencywide Documents Access and Management System (ADAMS).

ADAMS is accessible from the NRC wesite at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (610) 337-6953 or Steve Hammann, Senior Health Physicist, at (610) 337-5399 with any questions you may have regarding this letter.

Sincerely,

/RA/

Anthony Dimitriadis, Chief Decommissioning, ISFSI, and Reactor HP Branch Division of Nuclear Materials Safety Docket No: 50-289 License No: DPR-50 cc: Distribution via ListServ DOCUMENT NAME: G:\WordDocs\Current\Misc Letter\Three Mile Island Transition Letter.docx SUNSI Review Complete:

After declaring this document An Official Agency Record it will be released to the Public. ML19274B163 To receive a copy of this document, indicate in the box: C = Copy w/o attach/encl E = Copy w/ attach/encl N = No copy OFFICE DNMS/RI DNMS/RI DNMS/RI DRP/RI NAME SHammann/sh ADimitriadis/ad DATE 9/30/19 10/1/19 OFFICIAL RECORD COPY