ML19273C003
| ML19273C003 | |
| Person / Time | |
|---|---|
| Site: | Sequoyah |
| Issue date: | 03/26/1979 |
| From: | Murphy C NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Parris H TENNESSEE VALLEY AUTHORITY |
| Shared Package | |
| ML19273C004 | List: |
| References | |
| NUDOCS 7906180720 | |
| Download: ML19273C003 (2) | |
See also: IR 05000327/1979012
Text
. .
~.-
..
'?P 'jj
UNITED STATES
n aroug'o,
IO' N
.
NUCLEAR REGULATORY COMMISSION
'
%%[
f
g
,
REGloN 11
- -
t
101 M ARIETTA STREET. N.W.
ATLANTA, oEoRGIA 30303
%,*****/
NAR 2 61979
In Reply Refer To:
RII:CRM
50-327/79-12
50-328/79-7
Tennessee Valley Authority
ATTN:
H. G. Parris
Manager of Power
500A Chestnut Street Tower II
Chattanooga, TN 37401
Gentlemen:
This refers to the inspection conducted by Mr. C. R. McFarland of this office
on February 5-7, 1979, of activities authorized by NRC Construction Permit
Nos. CPPR-72 and CPPR-73 for the Sequoyah I and 2 facilities, and to the
discussion of our findings held with Mr. G. G. Stack at the conclusion of the
inspection.
Areas examined during the inspection and our findings are discusr. d in the
enclosed inspection report. Within these areas, the inspection corsisted of
selective examinations of procedures and representative records, interviews
with personnel, and observations by the inspector.
Within the scope of this inspection, no items of noncompliance were disclosed.
We have examined actions you have taken with regard to previously identified
enforcement matters and unresolved items.
The status of these items is
discussed in the enclosed report.
In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room. If this
report contains any information that you (or your contractor) believe to be
p rop rie . ..ry , it is necessary that you make a written application within
20 days to this office to withhold such information from public disclosure.
Any such application must include a full statement of the reasons on the
basis of rhich it is claimed that the information is proprietary, and should
be prepared so that proprietary information identified in the application is
contained in a separate part of the document. If we do not hear from you in
this regard within the specified period, the report will be placed in the
Public Document Room.
2353 067
790618 0 7AO -
~._
.__ _... ____..__ . _ . .
.
MAR 2 61979
i
Tennessee Valley Authority
-2-
Should you have any questions concerning this letter, we will be glad to
discuss them with you.
Sincerely,
b
C. E. Murphy, Chief
Reactor Construction and
Engineering Support Branch
Enclosure:
Inspection Report Nos.
50-327/79-12 and 50-328/79-7
cc w/ encl:
J. E. Gilleland
Assistant Manager cf Power
500C Chestnut Street Tower II
ChatLapooga, TN 37401
G. G. Stack, Project Manager
P. O. B.)x 2000
Daisy, TN 37319
J. M. Ballentine
Plant Superintendent
P. O. Box 2000
Daisy, TN 37319
2353 068
J. F. Cox
400 Commerce Street
W10C131 C
Knoxville, TN 37902
D. L. Lambert, Project Engineer
400 Chestnut Street Tower II
Chattanooga, TN 37401