Text
.
.'
s
UNITED STATES
[e' "IGugo,
NUCLEAR REGULATORY COMMISSION
,
REGION il
e
, .c3
g
101 M ARIETT A ST REET, N.W.
f
M
c
o..
8
ATLANTA, GEORGI A 30303
%n .' . . . . s '
APR 4
- 979
o
In Reply Refer To:
RII:CHW
50-335/79-06
Florida Power and Light Company
R. E. Uhrig, Vice President
Advanced Systems and Technology
P. O. Box 529'00
Miami, FL 33152
Gentlemen:
This refers to the inspection conducted by E. H. Webster of this office on
February 12-16, 1979, of activities authorized by NRC License No. DPR-67 for
the St. Lucie Unit I facility, and to the discussion of our findings held
with C. M. Wethy at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report.
Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews
with personnel, and observations by the inspector.
We have examined actions you have taken with regard to previously reported
unresolved items.
The status of these items is discussed in the enclosed
report.
One new unresolved item resulted from this inspection and is discussed in the
enclosed report.
This item will be examined during subsequent inspections.
During the inspection, it was found that certain activities under your license
appear to be in noncompliance with KRC requirements.
These items aad references
to pertinent requirements are listed in the Notice of Violation enclosed here-
with as Appendix A.
This notice is sent to you pursuant to the provisions of
Section 2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of
Federal Regulations.
Section 2.201 requires you to submit to this office,
within 20 days of your receipt of this notice, a written statement or expla-
nation in reply including:
(1) corrective steps which have been taken by you
and the results achieved; (2) corrective steps which will be taken to avoid
further noncompliance; and (3) the date when full compliance will be achieved.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room.
If this
report contains any information that you (or your contractor) believe to be
proprietary, it is necessary that you make a written application within 20
days to this office to withhold such information from public disclosure. Any
such application must include a full statement of the reasons on the basis of
2247
053
7906230oog{,
.
.
Florida Power and Light Company
-2-
gpg 4
g;
which it is claimed that the information is proprietary, and should be prepared
so that proprietary information identified in the application is contained in
a separate part of the document.
If we do not hear from you in this regard
within the specified period, the report will be placed in the Public Document
- Roem.
Should you nave any questions concerning this letter, we will be glad to
discuss them with you.
Sincerely,
'
,/)
' '
-
Y 'l
h
,
Richard C. Lewis, Acting Chief
Reactor Operations and Nuclear
Support Branch
Enclosure:
1.
Appendix A, Notice of Violation
2.
Inspection Report No. 50-335/79-06
cc w/ encl:
C. 5. Wethy, Plant Manager
P. O. Box 128
2247
054
Ft. Pierce, FL 33450
Nat Weems, Assistant QA Manager
P. O. Box 128
Ft. Pierce, FL 33450