Forwards IE Bulletin 78-12B, Atypical Weld Matl in Reactor Pressure Vessel Welds
ML19270F920
Person / Time
Site: Dresden, Byron, Braidwood, Quad Cities, Zion, LaSalle  Constellation icon.png
Issue date: 03/19/1979
From: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Brian Lee
COMMONWEALTH EDISON CO.
References
NUDOCS 7904030058
Download: ML19270F920 (1)


Text

,

(

j # ""'* %

UNITEo STATES

,t NUCLEAR REGULATORY COMMISSION

  • f ( f i $. i j REGION til i.

g 799 ROOSEVELT ROAD d'

GLEN E LLYN, lLLINOIS 60137 g

.s, www Docket Nos. 50-10, 50-237, 50-249, 50-254, 50-265, 50-295, 50-304, 50-373, 50-374, 50-454, 50-455, 50-456 and 50-457 Commonwealth Fdison Company ATTN:

Mr. Byron Lee, Jr.

Vice President Post Office Box 767 Chicago, IL 60690 Gentlemen:

Enclosed is a supplement (IE Bulletin No.78-12B) to IE Bulletin No. 78-12 and 12A which requires action by you with regard to your power reactor facilities with an operating license or a construction permit.

Should you have any questions regarding this Bulletin or the actions required by you, please contact this office.

Sincerely, Ak James G. Kep 1 r Director

Enclosures:

1.

IE Bulletin No.78-12B 2.

List of IE Bulletins Issued in Last Twelve Months cc w/encls:

Mr. B. B. Stephenson, Mr. R. Cosaro, Project Station Superintendent Superintendent Mr. N. Kalivianakis, Central Files Station Superintendent Director, NRR/DPM Mr. N. Wandke, Station Director, NRR/ DOR Superintendent PDR Mr. L. J. Burke, Site Local PDR Project Superintendent ljSIC Mr. T. E. Quaka, Quality y'fIC Assurance Supervisor Anthony Roisman, Esq.,

Mr. R. H. Holyoak, Station Attorney Superintendent Mr. Dean Hansell, Office Mr. Gunner Sorensen, Site of Assistant Attorney Project Superintendent General 7so40acoSg

\\

=.

U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT REGION III March 19, 1979 IE Bulletin No.78-12B ATYPICAL WELD MATERIAL IN REACTOR PRESSURE VESSEL WELDS Description of Circumstances:

This Bulletin is a supplement to IE Bulletins 78-12 and 12A and all three documents must be collectively considered to provide an adequate response to the bulletins.

Following the issuance of IE Bulletin 78-12A, members of the Office of Inspection and Enforcement staff met with representatives from the reactor vessel manufacturers and suppliers to discuss the requirements of the bulletins.

During these meetings, detailed interpretation of the data require =ents was provided based on the manufacturer's respective methods of fabrication and record systems.

Recognizing that the scope of the record review is extensive, additional time to respond to the bulletins is provided by this supplement.

Action to be Taken by Licensees and Permit Holders:

This bulletin applies to all power reactor facilities with an operating license or a construction permit, except those already identified as possibly having atypical weld material.

Responses to the requirements in Bulletins 78-12 and 12A shall be submitted in writing in accordance with the following schedule:

1.

Generic reports from each reactor vessel manufacturer shall

_he submitted to the NRC by May 1,1979.

2.

The licensee responses shall be submitted by May 29, 1979. Tha licensee's response shall include all of the specific vessel information required by the bulletir$ which is not covered by the vessel manufaqturers generic report and shall indicate that the licensee is satisfied that the generic report adequately represents data for the specific vessels covered by the licensee's report.

Approved by GAO, 3180225 (R0072); clearance expires 7/31/80. Approval was given under a blanket clearance specifically for identified generic problems.

}{}

1-t g o o s 4.. __ _.

l IE Bulletin No.78-12B March 19, 1979 LISTING OF IE BULLETINS ISSUED IN LAST TWELVE MONTHS Bulletin Subject Date Issued Issued To No.

78-05 Malfunctioning of 4/14/78 All Power Reactor Circuit Breaker Facilities with an Auxiliary Contact OL or CP Mechanism-General Model CR105X 78-06 Defective Cutler-5/31/78 All Power Reactor Hammer, Type E Relays Facilities with an With DC Coils OL or CP 78-07 Protection afforded 6/12/78 All Power Reactor by Air-Line Respirators Facilities with an and Supplied-Air Hoods OL, all class E and F Research Reactors with an OL, all Fuel Cycle Facilities with an OL, and all Priority 1 Material Licensees 78-08 Radiation Levels from 6/12/78 All Power and Tuel Element Transfer Research Reactor Tubes Facilities with a Fuel Element transfer tube and an OL.

78-09 BWR Drywell Leakage 6/14/79 All BWR Power Paths Associated with Reactor Facilities Inadequate Drywell with an OL or CP Closures 78-10 Bergen-Paterson 6/27/78 All BWR Power Hydraulic Shock Reactor Facilities Suppressor Accumulator with an OL or CP Spring Coils t

Page 1 of 2

4..

t IE Bulletin No.78-12B March 19, 1979 LISTING OF IE BULLETINS ISSUED IN LAST TWELVE MONTilS Bulletin Subject Date Issued Issued To No.

78-11 Fzamination of Mark I 7/21/78 BWR Power Reat. tor Containment Torus Facilities for Welds action:

Peach Bottom 2 and 3, Quad Cities 1 and 2, llatch 1, Monti-cello and Vermont Yankee 78-12 Atypical Weld Material 9/29/78 All Power Reactor in Reactor Pressure Facilities with an Tessel Welds OL or CP 38-12A Atypical Weld Material 11/24/78 All Power Reactor in Reactor Pressure Facilities with an Vessel Welds OL or CP 78-13 Failures In Source Heads 10/27/78 All general and of Kay-Ray, Inc., Gauges specific licensees Models 7050, 7050B, 7051, with the subject 7051B, 7060, 7060B, 7061 Kay-Ray, Inc.

and 7061B gauges 78-14 Deterioration of Buna-N 12/19/78 All GE BWR facilities Components In ASCO with an OL or CP Solenoids 79-01 Environmental Qualifica-2/8/79 All Tower Reactor tion of Class IE Equipment Facilities with an OL or CP 79-02 Pipe Support Base Plate 3/2/79 All Power Reactor Designs Using Concrete Facilities with an Expansion Anchor Bolts OL or CP 79-03 Longitudinal Weld Defects 3/12/79 All Power Reactor in ASME SA-312 Type 304 Facilities and an Stainless Steel Pipe OL or CP Spools Manufactured by Youngstown Welding and