Forwards QA Program Insp Rept 99900081/78-03 on 781030-1103 & Notice of Deviation
ML19270F598
Person / Time
Issue date: 11/22/1978
From: Potapovs U
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Owsley G
SIEMENS POWER CORP. (FORMERLY SIEMENS NUCLEAR POWER
Shared Package
ML19270F594 List:
References
REF-QA-99900081 NUDOCS 7902150488
Download: ML19270F598 (2)


Text

Soe.

g'8 "%,,

UNITED STAILS NUCLE AR H EGU LA TOlt Y COW,11SslON

[

~/*

'n itLGION IV

{ g g.

Gli HYAN PLAZA DRIVI!, SLA TE 1000

.[#

f AHunoTon. n xu ma n e

S2 f;;

-9 Docket !!o. 99900031/78-03 Exxon iluclear Company ATTt!:

Mr. G. F. Owsley Manager, Reload Licensing 2101 Horn Rapids Road Richland, Washington 99352 Gentlem.

This refers to the QA Program Inspection conducted by Mr. D. G. Anderson of this office on October 30 - November 3,1978, of your facility at Richland, Washington, and to the discussions of our findings with you and members of your staff at the conclusion of the inspection.

Areas examined during the QA Program inspection and our findings are discussed in the enclosed report. Within these areas, the inspection consisted of an examination of procedures and representative records, interviews with personnel, and observations by the inspector.

During this inspection it was found that the implementation of your Quality Assurance Program failed to veet certain MRC requirements.

The specific findings and references to the pertinent requirements are identified in the enclosures to this letter.

Please provide us within thirty (30) days a written statement containing, (1) a description of any steps that have been or will be taken to correct this item, (2) a description of any steps that have been or will be taken to prevent recurrence, and (3) the dates your corrective actions and preventive measures were or will be complet.ed.

In accordance with Section 2.790 of the Costission's " Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and your reply together with the enclosed inspection report will be placed in the Commission's Public Document Room.

If this report contains any information that you believe to be proprietary, it is necessary that you make a written application within thirty (30) days to this office to withhold such information from public disclosure.

Any such application must include a full statement of the reasons on the basis of which it is claimed that the information is proprietary, and should be prepared so that proprietary information identified in the application is contained in a separate part of the document.

If we do not hear from you in this regard within the specified period, the report will be placed in the Public Document Room.

7902150488

Exxon I;:rclear Coapany Should you have any questions concerning this inspecticn, we will be pleased to discuss them with you.

Sincerely, s -

b bd.t.,

1k hv)

Uldis Potapovs, Ckief Vendor Inspection Branch

Attachment:

1.

flotice of Daviation 2.

Inspection P,cport No. 99900031/78-03