VepCO February 1, 1979 Mr. James P. O'Reilly, Director Serial No. 661B Office of Inspection & Enforcement PSE&C/MBS:adw:mc U. S. Nuclear Regulatory Commission Region II Docket No. 50-339 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303
Dear Mr. O'Reilly:
In accordance with 10CFR50.55(e), the NRC, Region II, was not.ified on November 20, 1978 that spare containment pipe penetrations are not sealed at both ends as stated in the FSAR Section 6.2.4.3, Subsection 4, Page 6.2-125. On December 20, 1978, you were notified by an interim report that a final report would be submitted by February 1,1979.
Our engineering evaluation has determined the appropriate corrective action is to install welded caps on the outside containment ends of all 29 spare penetrations. This corrective action is in accordance with our com-mitment in the FSAR Section 6.2.4.3, Subsection 4, Page 6.2-125.
We consider this to be the final report under the provisions of 10CFR50.55(e).
Please contact me if further information is required.
Very truly yours,
$Y
/,E Sam C. Brown, Jr.
Senior Vice President Mr. John G. Davis, Acting Director cc:
Office of Inspection and Enforcement Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation 7902060116 9
5