Interim Rept 10,Initial Approach to Power Tests (B-Series), 781122-790222
ML19263E127
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 05/21/1979
From:
PUBLIC SERVICE CO. OF COLORADO
To:
Shared Package
ML19263E124 List:
References
NUDOCS 7906010223
Download: ML19263E127 (2)


Text

THE MRT ST. VRAIN INITIAL APPROAQi TO POWER TESIS (B-SERIES)

INTERIM REPORT 10 Report for Period Ending February 22, 1979 230] .45 <

7906010213

Interim Report 8 covering the 90 day period pending August 22, 1978, reported the coc:pletion of all tests up to 70% of plant load. Since the Nuclear Regulatory Con =ission did not release the plant for operations at power levels in excess of 70%, no further Initial Approach to Power Tests were performed during the 90 days ending February 22, 1979.

Future interim reports will report the results of any startup tests.