Forwards QA Program Insp Rept 99900510/04 on 781113-17 & Notice of Deviation
ML19263C554
Person / Time
Issue date: 12/04/1978
From: Potapovs U
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Curnane R
UNITED ENGINEERS & CONSTRUCTORS, INC.
Shared Package
ML19263C551 List:
References
REF-QA-99900510 NUDOCS 7902260547
Download: ML19263C554 (2)


Text

OM4

*e Mc,u UN!TED STATES 4

o NUCLEAR HECULATOHY COMMISSION

[T n

REGION IV 611 RYAN PLAZA DRIVE, SUITE 1000

[

ARLCJGTON, TEXAS 76011

%..-u p

December 4, 1978 Docket No. 99900510/78-04 United Engineers & Constructors, Inc.

Attn: Mr. R. A. Curnane, Vice President Project Support Operations 30 South 17th Strcet Philadelphia, Pennsylvania 19101 Gentlemen:

This refers to the QA Program Inspection conducted by Mr. J. R. Costello of this office on November 13-17, 1978, of your facility at Philadelphia, Pennsylvania, and to the discussions of our findings with Mr. J. B. Silverwood and members of your staff at the conclusion of the inspection.

Areas examined during the QA program inspection and our findings are discussed in the enclosed report. Within these areas, the inspection consisted of an examination of procetures and representative records, interviews with person-nel, and observations by the inspector.

During this inspection it was found that the implementation of your QA program failed to meet certain NRC requirements. The specific findings and references to the pertinent requirements are identified in the er. closures to this letter.

Please provide us within thirty (30) days a written statement containing, (1) a description of steps that have been or will be taken to correct these items, (2) a description of steps that have been or will be taken to prevent recurrence, and (3) the dates your corrective actions and preventive measures were or will be completed.

In accordance with Section 2.790 of the Commission's " Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter with enclosure and your reply together with the enclosed inspection report will be placed in the Commission's Public Document Room.

If this report contains any information that you believe to be proprietar you make a written application within thirty (30)y, it is necessary that days to this office to withhold such information frc, public disclosure.

Any such application must include a full statement of the reasons on the basis of which it is claimed that the information is proprietary, and should be prepared so that propri-etary information identified in the application is contained in a separate 7 9 0 2260 6Y 7

United Engineers & December 4, 1978 Constructors, Inc.

part of the document.

If we do not hear from you in this regard within the specified period, the report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely, (7

$dAt Z

nN, Uldis Potapovs, Chie Vendor Inspection Branch

Enclosures:

1.

Notice of Deviation 2.

Inspection Report No. 99900510/78-04

%