E

,r g" "G%,

UNITED STATES

/

g g

NUCLEAR REGULATOPY COMMISSION M

  • f(

j S REGION I e

3(

/j j F11 PARK AVENUE o,

jg KING OF PRUS$5 A, PENNSYLVANI A 19406

,f NOV 0 9 B76 i

Docket Nos. 70-1143 70-1684 Westinghouse Electric Corporation ATTN: Mr. W. J. Dollard General Manager Nuclear Fuel Division s

Nuclear Energy Systems P.O. Box 355 Pittsburgh, Pennsylvania 15235 q

Gentlemen:

Subject:

Combined Inspection 70-1143/78-16 and 70-1684/78-01 This refers to the inspection conducted by Mr. E. T. Shaub of this office on September 18 to October 25, 1978, at the Cheswick, Pennsylvania facility, of activities authorized by NRC License Nos. SNM-ll20 and XSNM-510 and to the discussions of our findings held by Mr. R. Summers of this office with Mr. J. Bastin of your staff at the conclusion of the inspection.

Areas examined during this inspection included the planned export ship-ment to Japan and review of associated production records. Within these ar" s, the inspection consisted of selective examinations of procedures ano representative records, interviews with personnel, measurements made by the inspector, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2, Title 10, Code of Federal Regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Fublic Document Room.

If this report contains any information that you (or your con-tractor) believe to be proprietary, it is necessary that you make a written application within 20 days to this office to withhold such information from public disclosure.

Any such application must be accompanied by an affidavit executed by the owner of the information, which identifies the document or part sought to be withheld, and which contains a statement of reasons which addresses with specificity the items which will be considered by the Commission as listed in subpara-graph (b)(4) of Section 2.790.

The information sought to be withheld shall be incorporated as far as possible into a separate part of the affidavit.

If we do not hear from you in this regard within the spec-ified period, the report will be placed in the Public Document Room.

790105o Wo

Westinghouse Electric Corporation 2

fiOV 0 9 1573 No reply to this letter is required; however, should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely, l

dY Walter G. Martin, Chief Safeguards Branch

Enclosure:

Office of Inspection and Enforcement Combined Inspection Report Numbers 70-1143/78-16 and 70-1684/78-01 cc w/ encl:

C. E. Anthony, General Manager, Electro Mechanical Division J. J. Bastin, Manager, Plutonium Fuels Development Laboratory R. P. DiPiazza, NES License Administrator 4