Forwards IE Insp Rept 50-346/79-32 on 791015-20,1101-02, 15-16 & 20.No Noncompliance Noted
ML19262C345
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 01/04/1980
From: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Crouse R
TOLEDO EDISON CO.
Shared Package
ML19262C346 List:
References
NUDOCS 8002110311
Download: ML19262C345 (2)


See also: IR 05000346/1979032

Text

/

o

UNITED STATES

8

f ,7,

NUCLEAR REGULATORY COMMISSION

$

fE

REGION lli

'

o

799 ROOSEVELT ROAD

i

8

\\, . . . . . ,o

G LEN '!LLYN. 8LLINOIS 60137

\\A

h

Docket No. 50-346

Toledo Edison Company

ATTN:

Mr. Richard P. Crouse

Vice President

Energy Supply

Edison Plaza

300 Madison Avenue

Toledo, OH 43652

Gentlemen:

This refers to the inspection conducted by Messrs. R. F. Warnick, J. D. Smith,

T. N. Tambling and L. A. Feyes of this office on October 15-20, November 1, 2,

15, 16 and 20, 1979, of activities at Davis-Besse Nuclear Power Station, Unit 3,

authorized by NRC Operating License No. NPF-3 and to the discussion of our

findings with Mr. T. Murray, Station Superintendent at the conclusion of the

inspection.

The enclosed copy of our inspection report identifies areas examined during

the inspection. Within these areas, the inspection consisted of a selective

examination of procedures and representative records, observations, and inter-

views with personnel.

No items of noncompliance with NRC requirements were identified during the

course of this inspection.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Pact 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspectian report will be placed in the NRC's Public Document Room, except as

follows.

If this report contains information that you ot your contractors

believe to be proprietary, you must apply in writing to this office, within

twenty daye of your receipt of this letter, to withhold such information from

public disclosure. The application must include a full statement of the reasons

for which the information is considered proprietary, and should be prepared so

that proprietary information identified in the application is contained in an

enclosure to the application.

1946 054

8002110QH

.

Toledo Edison Company

-2-

.

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

b

e

W

. F. Heishman, Chief

Reactor Operations and

Nuclear Support Branch

Enclosure:

IE Inspection

Report No. 50-346/79-32

cc w/ enc 1:

Mr. T. D. Murray, Station

Superintendent

Central Files

Reproduction Unit hTC 20b

PDR

Local PDR

NSIC

TIC

Harold W. Kohn, Power

Siting Commission

Helen W. Evans, State

of Ohio

1946 055