DAIRYLAND POWER COOPERATIVE
& G,,,,, O b n t.
54601 January 21, 1980 In reply, please refer to LAC-6743 DOCKET NO. 50-409 Director of Nuclear Reactor Regulation ATTN:
Mr. Dennis L.
Ziemann, Chief Operating Reactors Branch #2 Division of Operating Reactors U. S. Nuclear Regulatory Commission Washington, D. C.
20555
SUBJECT:
DAIRYLAND POWER COOPERATIVE LA CROSSE BOILING WATER REACTOR (LACBWR)
PROVISIONAL OPERATING LICENSE NO. DPR-45 APPLICATION FOR AMENDMENT TO LICENSE
Reference:
(1)
DPC Letter, LAC-6280, Linder to Ziemann, dated May 11, 1979.
(2)
DPC Letter, LAC-6429, Linder to Ziemann, dated July 27, 1979.
(3)
NRC Letter, Reid to Madgett, dated January 10, 1978.
(4)
License Amendment Fee, check #21046, dated July 10, 1979.
Gentlemen:
An application to amend Provisional Operating License No. DPR-45 was requested in Reference 1.
The requested snendment involved proposed changes to Technical Specifications for the La Crosse Boiling Water Reactor (LACBWR) which deal with the Inservice Inspection Program.
Reference 2 submitted the plans and requests for relief of the inservice testing and inspection programs for the La Crosse Boiling Water Reactor.
Subsequently, we have identified another area where inservice test-ing requirements of ASME Section XI are impractical.
Therefore, in accordance with the guidance of Reference 3, the attached relief request basis is submitted. of Reference 2 listed the valves to be included in the valve inservice testing program.
The atttched request has been placed in a format consistent with that of Enclosure 4 of Reference 2.
The information submitted in this application for license amendment has been reviewed by LACBWR Committees as prescribed in Technical Specifications.
g7 1g I
8001%B0 gg
~
Mr. Dennis L.
Ziemann, Chief LAC-6743 Operating Reactors Branch #2 January 21, 1980 The fee for the review of this license amendment was forwarded by Reference 4.
If you have any questions regarding this matter, please contact us.
Very truly yours, DAIRYLAND POWER' COOPERATIVE r
",wd
~
Frank Linder, General Manager FL:RW:af cc:
J. Keppler, Reg. Dir., NRC-DRO III State of Wisconsin )
)
COUNTY OF LA CROSSE)
Personally came before me this day of January, 1980, the above named Frank Linder, to me known to be the person who executed the foregoing instrument and acknowledged the same.
JL,J./hlbt.b Notary Public, La Crosse County Wisconsin.
My Commission expires March 2, 1980.
1816 268 RELIEF REQUEST BASIS VALVE:
64-25-001 CATEGORY :
A CLASS:
1 FUNCTION:
To allow bypassing the Main Steam Isolation Valve (64-30-001).
TEST RE-QUIREMENT:
Exercise valve for operability every three months.
BASIS FOR RELIEF:
To exercise this valve during plant operations would require inserting a signal which would also actuate the Main Steam Isolation Valve, resulting in a scram.
ALTERNATE TEST:
The valve will be exercised for operability each cold shutdown.