ML19262B381

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-282/79-27 & 50-306/79-21 on 791001-31.No Noncompliance Noted.Major Areas Inspected:Plant Operations, Maint,Security & Observations of Plant Staff Response to Steam Generator Tube Rupture
ML19262B381
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 11/13/1979
From: Feierabend C, Warnick R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19262B380 List:
References
50-282-79-27, 50-306-79-21, NUDOCS 7912210074
Download: ML19262B381 (9)


See also: IR 05000282/1979027

Text

.

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report Nos: 50-282/79-27; 50-306/79-21

Docket No: 50-282; 50-306

License No. DPR-42: DPR-60

Licensee: Northern States Power Company

414 Nicollet Mall

Minneapolis, MN 55401

Facility Name:

Prairie Island Nuclear Generating Plant, Units 1 and 2

Inspection At:

Prairie Island Site, Red Wing, Minnesota

Inspection Conducted: October 1-31, 1979

RftU pe,

Inspector:

C. D. Feierabend

//-/3- 7/

RFR)wk

Approved By:

R. F. Warnick, Chief,

//-/ 3 -79

Reactor Projects Section 2

Inspection Summay

Inspection on October 1-31, 1979 (Report No. 50-282/79-27; 50-306/79-21)

Areas Inspected: Routine resident inspection of plant operations, mainten-

ance, security, and observations of plant staff response to steam generator

tube rupture. The inspection involved 123 inspector-hours by the resident

-

inspector.

Results:

No items of noncompliance or deviations were identified.

2162 293

  • h7Y

7 912210

.

DETAILS

-

1.

Personnel Contacted

F. Tierney, Plant Manager

J. Brokaw, Plant Superintendent, Operations and Maintenance

E. Watzl, Plant Superintendent, Plant Engineering and

Radiation Protection

R. Lindsey, Superintendent, Operations

J. Nelson, Superintendeat, Maintenance

J. Hoffman, Superintendent, Technical Engineering

D. Schuelke, Superintendent, Radiation Protection

S. Fehn, Senior Scheduling Engineer

G. Sundberg, Instrument Engineer

G. Edon, Shift Supervisor

P. Ryan, Shift Supervisor

M. Balk, Shift Supervisor

J. Meath, Shift Supervisor

D. Walker, Shift Supervisor

2.

General

Unit 2 operated routinely throughout the month.

Unit I was shut down

from October 2-23 to repair a ruptured steam generator tube. The licen-

see continued inspection and upgrading of pipe support base plates and

seismic design pipe supports in response to IE Bulletins IEB 79-02 and

IEB 79-14 during the outage.

3.

Steam Generator Tube Rupture

At approximately 2:45 p.m. on October 2, 1979 t!.e inspector heard

announcement of Unit I safety injection on the plant page and

proceeded immediately to the control room. The inspector was informed

that the apparent cause was a tube rupture in a steam generator.

The

inspector verified that the air ejector offgas monitor was offscale

(high) and that the pressurizer level and pressure had dropped (level

was offscale low). The inspector observed that a member of the plant

staff had the emergency procedure for steam generator tube rupture and

that automatic actions were being verified.

As soon as immediate response was complete a licensee supervisor ini-

tiated communication with the emergency response centers in IE Head-

quarters and in the Region III office.

The Resident Inspector coor-

dinated communications with the response centers until all systems

were stable.

The licensee plant staff performed professionally in identifying the

problem and in implementing emergency procedures.

2)b

-2-

.

The Region III emergency response team arrived onsite at approximately

6:50 p.m. to provide independent assessment and monitoring. Results

of the

rgency team efforts are described in a separate inspection

report

The licensee proceded to place the plant in cold shutdown to identify

the ruptured tube, to determine the cause of the gbe failure, and

to complete repairs. The licensee's event report- , accurately des-

cribes the sequence of events, inspection and identification of the

cause and corrective actions completed prior to restart.

Messrs. B. D. Liaw, NRR, and K. D. Ward, IE Region III, participated

in the licensee's examination and observed portions of the licensee's

inspection of the steam generat

. These activities were described

in a separate inspection report

After completion of repairs and inspection of the steam generator,

the licensee proceeded to restart the plant in accordance with

approved procedures.

Prior to restart the Resident Inspector veri-

fied that the licensee had fulfilled commitments made to NRR during

a meeting in Bethesda, Maryland on Octobe E16, 1979. The commitments

were that the events would be documented in a report and available

for review by NRR and that the licensee would implement administrative

controls regarding iodine limits.

4.

Plant Operations

The inspector reviewed plant operations including examination of

selected operating logs, special orders, temporary memos, jumper and

tagout logs for the month of October.

Tours of the plant included

walks through the various areas of the plant to observe operations

and activities in progress, to inspect the status of monitoring and

instruments, to observe for adherence to radiation controls and fire

protection rules, to check proper alignment of selected valves and

equipment controls, and to review status of various alarmed annun-

ciators with operators.

The inspector also reviewed annunciator status, recorder charts,

surveillance records, and logs to serify that plant operations were

maintained in accordance with Technical Specification requirements.

1/

IE Inspection Report No. 50-282/79-26

2/

P-R0-79-27, Tube Rupture in No. 11 Steam Generator, dtd October 16, 1979.

3/ IE Inspection Report No. 50-282/79-25

2162 295

-3-

.

.

The inspector performed independent verification of selected plant

systems and instrumentation during the licensee's preparations for

heatup after repairs to the steam generator were complete.

Check-

lists completed included:

C1.1.4-1, Reactor Coolant System

C1.1.5-1, Rod Control and Position Indicating Systems

C1.1.9-1, Nuclear Instrumentation System, Part 1

The inspector also verified valve positions for portions of the

auxiliary feedwater, safety injection, residual heat removal, and

component cooling systems, and reviewed completed checklists to

confirm that the plant staff had completed system checks and survei-

llance tests required to be completed before heatup.

No items of noncompliance or deviations were identified.

5.

Security

The inspector conducted periodic observations of access control,

issuing badges, vehicle inspection, escorting, and communication

checks.

No items of noncompliance or deviations were identified.

6.

Maintenance

The inspector reviewed several work requests (WR's) and work request

authorizations (WRA's) and verified that all required reviews and

approvals had been completed. The inspector observed work in progress

during troubleshooting of controls for a Unit 1 power operated

relief valve and restoration to service.

The inspector also observed work in progress in Unit I containment

during inspection and repair of the No. 11 steam generator and

during repairs to cooling water system seismic restraints.

No items of noncompliance or deviations were identified.

7.

Licensee Event Reports (LERs)

The inspector reviewed the following LERs submitted by the licensee,

determined that reporting requirements had been met, and determined

that corrective actions were being implemented. (Closed)

P- 0-78-21 Excessive Leakage through Unit 2 Containment Purge

a.

Supply Valves

2}b

-4-

'

The licensee has submitted an update report to identify the cause

and corrective actions. Purge valves remain closed under admin-

istrative control.

b.

P-RO-79-17 Loss of both source range channels at shutdown

c.

P-LO-79-22 Instrument drift, Steam exclusion system

d.

?-RO-79-26 Axial offset outside target band

e.

P-R0-79-27 Tube Rupture in No. 11 Steam Generator (See Para-

graph 3 above)

8.

Exit Interview

The inspector conducted an exit interview with Mr. Tierney at the

conclusion of the inspection.

The inspector discussed the scope and

results of the inspection and stated that no items of noncompliance

or deviations were identified.

Attachment:

Preliminary

Inspection Findings

2162

297

-5-

OFFICE OF INSPECTION AN.' IN.T.iOLN!:. *

O

d

'

Fnr.LIMINARY INSPECTION FINDINGS

.

.

, . . , . . - .

. . _ . _ . . . -

. - . ,

_ .

_ . _ _ -

_ _ _ .

l'

1.

LICENSEE

l 2.

REC 10NAL O!'l'1CE

Northern States Power Company

U.S. Nuclear Regulatory Comission

414 Nicollet Mall

Office of Inspection & Enforcemen*, RIII

'

?!inneapolis, MN 55401

799 Roosevelt Road

Prairie Island 1 (Redwing, MN)

Glen Ellyn, IL 60137

Prairie Island 2 (Redwing, MN)

.

3.

DOCKET N"MBERS

4.

'! CENSE N"M3ERS

5.

DATE OF INSPECTION

50-282: 50-306

i

DPR-42: DPR 6^~

t

6kror u I- V /1/9

],

6.

'n'ithin the scope of the inspection, no itens of nonconpliance or deviation

were found.

7.

The following eatters are preliminary inspection findings:

(

.

&

,

.

.

2162

298

.

.

m.

[

8.

These preliminary inspection findings vill be reviewed by NRC Supervision /

'

Mar.agenent at the Region III Office and they will correspond with you

-

concerning any enforcenent action.

/

7

.

Nuc1 ear Re. ,.tery c - -

--

-

O

lfi

h

I /3I

0FFICE OF INSPECT 20N ANO INPJ.10I.'22.<

~

b

'u

U3b$j JtR!/dL=

-

.

.

./

??r. LIMINA 7.Y INSPECT:0N F:5"JINCS

.

,

'

'

..

.

s,

s..

. ~ ,. - - . -


vs.~n.+~~~=w-~~+-*

- - - -

-

  • - - - -

- - - *

f

1.

LICENSES

2.

R2010NAL O!'!!!CE

Northern States Power donpany'

" S. Nucient Reguintory Com ission

.

.

414 Nicollet Mall

'!inneapolis, MN 55401

'

Office of Inspection & Enforcement. RI!!

799 Roosevelt Road

"

7"'

Prairie Island 1 (Redving. MN)

~

Prairie Island 2-(Redving. MN)

-

-

3.

DOCKET N'33ERS

4

1.: CENSE N"M3ERS

5.

DATE OF INSPECTION

50-282: 50-306

??R-42: DPR 60

g 7effy

7~ l 2> N7 f

]

6.

'a'ithin the scope of the inspection, no itens of noncompliance or deviation

were found.

9

7.

The folleving natters are preliminary inspection findings:

(.-

.

'

.

-

.

4

.

.,

,

.

,

.

i

.

.

.

.

.

.

2162

299

-

.

.

.

i

S.

These preliminary inspection findings vill be reviewed by N"C Supervicion/

Management at the Regien I" Cffice and they vill correspond with you

-

concerning any enforcement action.

,

Neelear Rer"'.ntory rn- e e-

-

.

0FFICE OF INS."ECTION AN." IN.T.10L'22. '-

3

'

-

.

/.

PREL!v.INA7Y INS?ECTION FIS"JINGS

.

.-

-

-

.

___-;..--

- - . - . . -

, , _ , , , , . . _ _

,

1.

L!cENSEE

! 2.

'tEC10.N'AL Olf!!!CE

,

.

Northern States Po w. co pany

" S. Nuclear Regulatory Com-ission

.

'

414 Nicollet Mall

l

Office of Inspection L Enforce ent, n,::

'!inneapolis, MN 35401

799 Roosevelt Road

Glen Ellyn, IL 60137

Prairie Island 1 (Redving, MN)

Prairie Island 2 (Redving, MN)

-

.

3.

DOCKET N','MBERS

4

  • CINSE N"M3ERS

5.

DATE OF INSPECTION

DPR-42: ""2 6^~

M

50-282: 50-306

}.I ~ 2c))fff

i

~

l

L/

,

6.

'a'ithin the scope of the inspection, no itens of nonconpliance or deviation

-'

were found.

-

t

7.

The folleving eatters are preliminary inspection findings:

('

.

.

..

.

.

I

.

,

.

.

,

.

.

,

.

.

.

.

.

2162

.300

-

.

l S.

These preliminary inspettien findinge vill be reviewed by NRC Supervit: ion /

'

Managenent at the Region :: Office and they will correspond with you

-

concerning any enforcenent cetion.

/

-

dA

NUCleU T Re."'Q.a t.nry Cr** d e" '

-

.,

-

-

.

,

ori:Cr 07 1Nstsc::0N AN.n is.":.x:c.c....

y

g\\ 9 m}n

\\

g

. .

.

,

.;

gLg

@u

M3U

U

h

.

/<

?RELIMINARY INS?ECTION FINDINGS

.

.

.

.,

0

__.._m...--

_. ___

_-

_ _ - .

- _ . .

-

~ . . . . _ _

.,

1.

LICENSEE

2.

EC10NAL 01'FICE

.

,

Northern States Power dompany'

U.S. Nucl. ear Regulatory Comission

.

414 Nicollet Mall

Office of 1r.9pection 4 Enforcement. RIII

'inneapolis, MN 35401

799 Roosevelt Road

Prairie Island 1 (Redving, MN)

Glen Ellyn, IL 60137

Frairie Island 2 (Redving, MN)

-

.

l

3.

DOCKET N"MBERS

l4

1,: CENSE N"M3ERS

5.

DATE OF INS?ECTION

50-282: 50-306

.I

""R-4 2 "~ DR 66

h

2 / .5 f /97f

~

'

1

~

}*,

6.

'a'ithin the scope of the inspection, no itens of noncompliance or deviation

Vere found.

d

-

I

7.

The fo11oving natters are preliminary inspection findirgot

.

-

.

f

,

.

. .

.

I-

.

  • l

.

i

.

.

.

.

,

,

a

.

2162

301

4

.

Y

l S.

These preliminary inspection findinge vill be reviewed by NRC Supervicien/

r

Management at the Region ::: Office and they vill correspond with you

-

concerning any enforcement action.

.

Neelear R'ec catory cn

< e- '

-