Forwards IE Insp Repts 50-339/79-23,50-404/79-01 & 50-405/79-01 on 790410-12.No Noncompliance Noted
ML19261D853
Person / Time
Site: North Anna  
Issue date: 04/25/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Proffitt W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
Shared Package
ML19261D854 List:
References
NUDOCS 7906260524
Download: ML19261D853 (2)


See also: IR 05000339/1979023

Text

.. .

-

j

s

go-337

UNITED STATES

15P,6

f/opr

e# RE%q#o,,

NUCLEAR REGULATORY COMMISSION

[

}

REGION il

o

5

-.

t, $

101 MARIETT A STREET.N.W.

'8

ATLANTA, GEORGI A 30303

% , , , g +'

APR 2 51979

In Reply Refer To:

.

RII:CRM

50-339/79-23

50-404/79-1

50-405/79-1

Virginia Electric and Power Company

ATfN:

W. L. Proffitt

Senior Vice President, Power

P. O. Box 26666

Richmond, VA 23261

Gentlemen:

This refers to the inspection conducted by C. R. McFarland of this office on

April 10-12, 1979, of activities authorized by NRC Construction Permit Nos.

CPPR-78, CPPR-114 and CPPR-115 for the North Anna Power Station Unit 2, 3

and 4 facilities, and to the discussion of our findings held with E. R. Bane

at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews

with personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were

disclosed.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,

Title 10, Code of Federal Regulations, a copy of tnis letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe to be

proprietary, it is necessary that you make a written application within

20 days to this office to withhold such information from public disclosure.

Any such application must include a full statement of the reasons on the

basis of which it is claimed that the information is proprietary, and should

be prepared so that proprietary information identified in the application is

contained in a separate part of the document.

If we do not hear from you in

this regard within the specified period, the report will be placed in the

Public Document Room.

2313 207

7 9 0 6 2 6 06~M

. _ _ _

_ _

..

.

,

-

gpp 2 51979

v

Virginia Electric and Power

-2-

Company

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

.

Sincerely,

.

.

,

C. E. Murphy, Chief

Reactor Construction and Engineering

Support Branch

Enclosure:

Inspection Report Nos. 50-339/79-23,

50-404/79-1 and 50-405/79-1

cc w/ enc 1:

W. R. Cartwright, Station Manager

Box 402

Mineral, VA 23117

P. G. Perry

Senior Resident Engineer

P. O. Box 38

Mineral, VA 23117

2313

208

.

..

we