Forwards QA Program Insp Rept 99900053/79-01 on 790221-23 & Notice of Deviation
ML19261D391
Person / Time
Issue date: 04/06/1979
From: Potapovs U
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Caron A
ANCHOR/DARLING VALVE CO.
Shared Package
ML19261D382 List:
References
REF-QA-99900053 NUDOCS 7906190052
Download: ML19261D391 (2)


Text

-

pn me%

UNITED STATES ff o

NUCLEAR REGULATORY COMMISSION o

REGION IV 3

3.) A'

.. E 611 RYAN PLAZA DRIVE, SUITE 10G0

  • [w[/

pi AR LINGTON, TEXAS 76011 o

mun Docket No. 99900053/79-01 Anchor / Darling Valve Company Attn: Mr. A. E. Caron President One Belmont Avenue, Suite 320 Bala Cynwyd, Pennsylvania 19004 Gentlemen:

This refers to the QA Program inspection conducted by Mr. William D. Kelley of this office on February 21-23, 1979, of your facility at Williamsport, Pennsylvania, associated with the manufacture of ASME Section III "N" Class 1, 2 and 3 valves, and to the discussions of our findings with Mr. W. G. Knecht and members of your staff at the conclusion of the inspec-tion.

This inspection was-made to confinn that, in the areas inspected, your QA Program is being effectively implemented. The inspection effort is not designed to assure that unique quality requirements imposed by a customer are being implemented; nor to assure that a specific product, component or service provided by you to your customers, is of acceptable quali ty. As you know, the NRC requires each of its licensees to assume full responsibility for the quality of specific products, components or services procured from others. You should therefore not conclude that the NRC's inspection exempts you from inspections by an NRC licensee or his agents nor from taking effective corrective action in response to their findings.

Areas examined and our findings are discussed in the enclosed report.

Within these areas, the inspection consisted of an examination of procedures and representative records, interviews with personnel, and observations by the inspector.

During the inspection it was found that the implementation of your QA Program failed to meet certain NRC requirements. The specific findings and references to the pertinent requirements are identified in the enclosures to this letter.

Please provide us within thirty (30) days of your receipt of this report a written statement containing, (1) a description of steps that have Men or will be taken to correct these items, (2) a description of steps that have been or will be taken to prevent recurrence, and (3) the date your corrective actions and preventive measures were or will be completed.

7906190052 2308 177

Anchor Darling Valve Company In accordance with Section 2.790 of the Commission's " Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter with enclosure and your reply,.together with the enclosed ins [.!ction report will be placed in the Comnission's Public Document Room.

If this report contains any information that you believe to be proprietary, it is necessary that you make a written application within thirty (30) days to this office to withhold such information from public disclosure. Any such application must include a full statement of the reasons on the basis of which it is claimed that the information is proprietary, and should be prepared so that proprietary information identified in the application is contained in a seaarate part of the document.

If we do not hear from you in this regard within the specified period, the report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

--~--_._._.__ _

Sincerely, Uldis otapovs, C i f Vendor Inspection Branch

Enclosures:

1.

Notice of Deviation 2.

Inspection Report No. 99900053/79-01 cc: Anchor Darling Valve Company Attn: Mr. G. W. Kneiser Quality Assurance Manager 701 First Street 2308 178 Williamsport, Pennsylvania 17701

,