~Qh24 dm arcg'o, UNITED STATES ja NUCLEAR REGULATORY COMMISSION
[p7 REGION IV 2 3A 611 RYAN PLAZA ORIVE,SulTE 1000
- d AR LINGTON, TE X AS 76011 February 22, 1979 Docket flo. 99900087/79-01 Walworth Company Aloyco Plant Attn: Mr. A. A. Obeid Plant Manager 1400 West Elizabeth Avenue Linden, tiew Jersey 07036 Gentlemen:
This refers to the QA Program inspection conducted by William D. Kelley of this office on January 22 & 25, 1979, of your corporate office in King -
of Prussia PA and your Aloyco plant in Linden, flew Jersey, associated with the manufacture of ASME Section III "fl" Class 1, 2 & 3 valves and to the discussion of our findings with you and members of your staff at the conclusion of the inspection.
This inspection was made to confirm that, in the areas inspected, your QA Program is being effectively implemented. The inspection effort is not designed to assure that unique quality requirements imposed by a customer are bding implemented; nor to assure that a specific product, component or service provided by you to your customers, is of acceptable quality. As you know, the f4RC requires each of its licensees to assume full responsibility for the quality of specific products, components or services procured from others.
You should therefore not conclude that the flRC's inspection exempts you from inspections by an flRC licensee or his agents nor from taking effective corrective action in response to their findings.
Areas examined during the inspection and our findings are discussed in the enclosed report.
Within these areas, the inspection consisted of an examination of procedures and representative records, interviews with personnel, and observations by the inspector.
Within the scope of this inspection, we found no instance where you failed to meet flRC requirements.
In accordance with Section 2.790 of the Commission's " Rules of Practice,"
Part 2, Title 10, Code of Federal Regulations, a copy of this letter together with the enclosed inspection report will be placed in the Commission's Public Document Room.
If this report contains any infoma-tion that you believe to be proprietary, it is necessary that you make a written application within thirty (30) days to this office to with-hold such information from public disclosure. Any such application must include a full statement of the reasons on the basis of which it is 790427 o1 %
Walworth Company February 22, 1979 claimed that the information 's proprietary, and should be prepared so i
that proprietary information identified in the application is contained in a separate part of the document.
If we do not hear from you in this regard within the specified period, the report will be placed in the Public Document Room.
Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
Sincerely, f
[C L,
&c.(2,yp Uldis Potapovs, Chief 1 Vendor Inspection Branch
Enclosure:
Inspection Report No.
99900087/79-01 cc:
Walworth Company ATTN: Mr. R. O. Hunt Director of Quality Assurance P. O. Box 873 Valley Forge, Pennsylvania 19482
/