Forwards IE Insp Repts 50-266/78-18 & 50-301/78-21 on 781004-06 & 24-27.No Noncompliance Noted
ML19261A368
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 12/06/1978
From: Davis A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Burstein S
WISCONSIN ELECTRIC POWER CO.
Shared Package
ML19261A369 List:
References
NUDOCS 7901110350
Download: ML19261A368 (2)


See also: IR 05000266/1978018

Text

T

e

'

TE/R

-

g

4,

UNITED STATES

'

. , .

?t

NUC LE AR REGULATORY COMMISSION

f I, ([ .I

REGION til

  • j

j

799 RooSEVE LT ROAD

,

$'s,

y

&

G LEN E LLYN, ILLINOIS 60137

.....

DEC 0 6 378

-

Docket No. 50-266

Docket No. 50-301

Wisconsin Electric Power Company

ATTN:

Mr. Sol Burstein

Executive Vice President

Power Plants

231 West Michigan

Milwaukee, WI 53201

Gentlemen:

This refers to the inspection conducted by Mr. L. R. Greger of

this office on October 4-6 and 24-27, 1978, of activities at the

Point Beach Nuclear Plant authorized by NRC Licenses No. DPR-24

and No. DPR-27 and to the discussion of our findings with Mr. Reed

and others of your staff at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas

examined during the inspection. Within these areas, the

inspection c^nsisted of a selective examination of procedures

and representative records, observations, and interviews with

personnel.

No items of noncompliance with NRC requirements were identified

during the course of this inspection.

In accordance with Section 2.790 of the NRC's " Rules of

Practice," Part 2, Title 10, Code of Federal Regulations,

a

copy of this letter and the enclosed inspection report will

be placed in the NRC's Public Document Room, except as follows.

If this report contains information that you or your contractors

believe to be proprietary, you must apply in writing to this

office, within twenty days of your receipt of this letter, to

withhold such information from public disclosure. The

application must include a full statement of the reasons for

which the information is considered proprietary, and should be

prepared so that proprietary informacion identified in the

application is contained in an enclosure to the application.

m

.)..I

3

350

.

.

DEC 06 JTS

Wisconsin Electric Power

-2-

Company

-

We will gladly dit uss any questions you have concerning this

inspection.

Sincerely,

.

O

.-

-

OBA-

A. B. Davis, Chief

Fuel Facility and

Materials Safety Branch

Enclosure:

IE Inspection

Rpts No. 50-266/78-18

and No. 50-301/78-21

cc w/ encl:

Mr. G. A. Reed, Manaher

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

-