Advises That Insp of Both Sides of Discs on Low Pressure Spindles Should Be Conducted Based on Review of Info Provided by Util & Presented by Westinghouse at 791217 Meeting.Forwards Request for Addl Info for Review
ML19260E113
Person / Time
Site: Point Beach NextEra Energy icon.png
Issue date: 12/27/1979
From: Schwencer A
Office of Nuclear Reactor Regulation
To: Burstein S
WISCONSIN ELECTRIC POWER CO.
References
NUDOCS 8002130380
Download: ML19260E113 (3)


Text

-

).. f

,(pa nec

[0,,

o UNITED STATES y, e(3 g NUCLEAR REGULATORY COMMISSION

g *f.
\\; G /

E WASHING TON. D. C. 20555 Decenber 27, 1979 Docket No. 50-266 Mr. Sol Burstein Executive Vice President Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, Wiscor.:ia 53201 I

Dear Mr. Burstein:

I Based on our review of the information yo. provided with respect to the recent low pressure turbine rotor inspection at Point Beach Unit No.1, l

our discussions with Westinghouse Electric Corporation at a meeting in Bethesda on December 17, 1979, and further discussions with your staff following this meeting, we believe that ar inspection of both sides of all discs on both low pressure spindles stould be conducted. This i

inspection should be perfortned at your neit scheduled shutdown (60 effective full power days following November 30,1979), or earlier if an opportunity arises. We request that the results of this inspection be reported to us prior to resuming opera-ion.

We have also determined that we will need the additional information identified in the enclosure to continue o.r review of this matter.

A response is requested within 30 days of your receipt of this letter.

Please contact us if you have any questiors concerning this request.

Sin:erely,

/ lQOddd6L A. Schwencer, Chief Operating Reactors Branch #1 Division of Operating Reactors

Enclosure:

Request for Additional Informa tion

w/ enclosure See next page 8002130 h

Mr. Sol Burstein Wisconsin Electric Power Company December 27, 1979 cc:

Mr. Bruce Churchill, Esquire l

Shaw, Pittman, Potts and Trowbridge 1800 M Street, N.W.

Washington, D. C.

20036 Document Department University of Wisconsin Stevens Point Library Stevens Point, Wisconsin 54481 Mr. Glenn /

Reed, Manager Nuclear Operations i

Wisconsin Electric Powe'r Company Point Beach Nuclear Plant 6610 Nuclear Road Two Rivers, Wisconsin 54241 r

t i

1 l

L

REQUEST FOR ADDITIONAL INFORMATION 1.

Provide the critical crack size for the bore in a format similar to that presented in Table IV of }l, letter dated December 20, 1979.

2.

Provide a current assessment of potential turbine missile consequences both at 1800 rpm and 132% overspeed.

3.

You are requested to expedite the submittal of the report of the October 1979 turbine rotor inspection.

6