[p *ue ,Io

v

UNITED STATES

h,4

  • )

- o

e

NUCLEAR REGULATORY COMMISSION

$ {%

'3 $

RE9CN lli

o,

g

799 ROeSEVELT ROAD

%

t

,o '

GLEN ELLYN, ILLINOIS 60137

.....

'JAN3

F

Docket No. 50-461

Illinois Power Company

ATTN:

Mr. W. C. Gerstner

Executive Vice President

500 South 27th Street

Decatur, IL 62525

Gentlemen:

This refers to the inspection conducted by Messrs. H. M. Wescott and

E. W. K. Lee of this office on December 4-6, 1979, of activities at the

Clinton Power Station, Unit 1, authorized by NRC Construction Permit No.

CPPR-137 and to the discussion of our findings with Messrs. M. Brashear

and J. Hampton and others of your staff at the conclusion of the inspec-

tion.

The enclosed copy of our inspection retort identifies areas examined

during the inspection. Within these areas, the inspection consisted of

a selective examination of procedures and representative records, obser-

vations, and interviews with personnel.

No items of noncompliance with NRC requirements were identified during

the course of this inspection.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

Room, except as follows.

If this report contains information that you

or your contractors believe to be proprietary, you must apply in writing

to this office, within twenty days of your receipt of this letter, to

withhold such information from public disclosure. The application must

include a full statement of the reasons for which the information is con-

sidered proprietary, and should be prepared so that proprietary informa-

tion identified in the application is contained in an enclosure to the

application.

19h)

220

8002080 ore

-

,

.

Illinois Power

-2-

' DAN ,5

7cen

Company

4

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

..

,

,.h hc'?EA

G. Fiorelli, Chief

Reactor Construction and

Engineering Support Branch

Enclosure:

IE Inspection

Rpt. No. 30-461/79-12

cc w/ encl:

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

Mr. Dean llansell, Office of

Assistant Attorney General

1943