ML19260D058

From kanterella
Jump to navigation Jump to search
Forwards Final Deficiency Rept Re Omission of Vertical Reinforcing Steel in Shear Wall Separating Fuel Handling Bldg & Reactor Auxiliary Bldg
ML19260D058
Person / Time
Site: Satsop
Issue date: 01/31/1980
From: Strand N
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Engelken R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
Shared Package
ML19260D059 List:
References
NUDOCS 8002070312
Download: ML19260D058 (1)


Text

~

_ P P

W shington Public Power Supply System A JOINT OPERATING AGENCY S

P. O. 80X 1223 ELM A. W ASHINGTON 98541 PHONE [206) 249 5001 January 31, 1980 G03-80-199 U. S. Nuclear Regulatory Commission Region V 1990 North California Boulevard Suite 202, Walnut Creek Plaza Walnut Creek, California 94596 Attention:

Mr. R. H. Engelken Director of Regulatory Operations

Dear Mr. Engelken:

Subject:

WPPSS NUCLEAR PROJECT NO. 3 DOCKET NUMBER 50-508 REPORTABLE DEFICIENCY, 10CFR50.55(e)

DEFECT / NONCOMPLIANCE REPORT N0. 008

Reference:

G03-79-2253, N. O. Strand to R. H. Engelken, same subject, dated December 3, 1979.

In accordance with the provisions of 10CFR50.55(e), your staff was informed by telephone on November 2, 1979 of a reportable condition involving the omission of vertical reinforcing steel in the shear wall separating the WNP-3 Fuel Handling Building and the Reactor Auxiliary Building. Attached is our final report concerning this deficiency.

All corrective action discussed in the final report will be imple-mented prior to our targeted placement of February 15, 1980.

Please contact us if you require additional information.

Very truly yours,

'b N. 0. STRAND -

~

Managing Director Attachments cc: