YA
"
UNITED STATES
[g yg
o
NUCLEAR REGULATORY COMMisslON
O5-
' , *
n
REGION l
hkM
j
631 PARK AVENUE
- gv
~f
KING OF PR USSI A, PENN5YLVANIA 19406
,
%*****/
OCT 31 1979
Docket No. 50-271
Vermont Yankee Nuclear Power Corporation
ATTN:
Mr. Robert H. Groce
Licensing Engineer
20 Turnpike Road
Westborough, Massachusetts 01581
Gentlemen:
Subject:
Inspection 50-271/79-16
This refers to the inspection conducted by Mr. R. Zimmerman of this office on
October 16-19, 1979 at Vermont Yankee Nuclear Power Station, Vernon, Vermont of
activities authorized by NRC License No. DPR-28 and to the discussions of our
findings held by Mr. Zimmerman with Mr. W. Conway and other members of your
staff at the conclusion of the inspection.
Areas examined during this inspection are described in the Office of Inspection
and Enforcement Inspection Report which is enclosed with this letter.
Within
these areas, the inspection consisted of selective examinations of procedures
and representative records, interviews with personnel, and observations by the
inspector.
Our inspector also verified the steps you have taken to correct the item of
noncompliance brought to your attention in a letter dated September 15, 1978.
We have no further questions regarding your action at this time.
Within the scope of this inspection, no items of noncompliance were observed.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title
10, Code of Federal Regulations, a copy of this letter and the enclosed inspection
report will be placed in the NRC's Public Document Room.
If this report contains
any information that you (or your contractor) believe to be proprietary, it is
necessary that you make a written application within 20 days to this office to
withhold such information from public disclosure.
Any such application must be
accompanied by an affidavit executed by the owner of the information, which
identifies the document or part sought to be withheld, and which contains a
statement of reasons which addresses with specificity the items which will be
considered by the Comission as listed in subparagraph (b) (4) of Section
2.790. The information sought to be withheld shall be incorporated as far as
possible into a separate part of the affidavit.
If we do not hear from you in
this regard within the specified period, the report will be placed in the Public
Document Room.
O
\\6W \\bb
7912180
.
Vermont Yankee Nuclear Power
2
OM $ I S
Corporation
No reply to this letter is required; however, if you should have any questions
concerning this inspection, we will be pleased to discuss them with you.
Sincerely,
t
'
/
1
n
. Brunner, Chief
Rea'ctor Operations and Nuclear
S'upport Branch
Enclosure: Office of Inspection and Enforcement Inspection
Report Number 60-271/79-16
cc w/ encl:
W. F. Conway, Plant Superintendent
Ms. J. Abbey, Technical Secretary
\\\\
16M
164