ML19260A538

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-352/79-07 & 50-353/79-07 on 790705-06 & 09. Noncompliance Noted:Failure to Follow Design Requirement for Welding of safety-related Pipe Restraint
ML19260A538
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 09/20/1979
From: Mattia J, Mcgaughy R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML19260A533 List:
References
50-352-79-07, 50-352-79-7, 50-353-79-07, 50-353-79-7, NUDOCS 7911210420
Download: ML19260A538 (6)


See also: IR 05000352/1979007

Text

.

.

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

Region I

50-352/79-07

Report No.

50-353/79-07

50-352

Docket No.

50-353

CPPR-106

License No. CPPR-107

Priority

Category

A

--

Licensee:

Philadelphia Electric Comoany

2301 Market Street

Philadelphia, Pennsylvania

19101

Facility Name:

Limerick Gneration Station, Units 1 and 2

Inspection at:

Limerick, Pennsylvania

Inspection co ducted: July 5, 6, and 9,1979

Inspectors:

A

9 [, F

j

,.

M Mattia, Reactor Inspector

date signed

cate signed

date signed

Approved by: [/1/ M/h@#.5

0/79

R. McGau'ghy, Chie[d/ojects Section,

/ date signed

'

RC&ES Branch

Inscection Summary:

Unit 1 Inspection on July 5, 6, and 9, 1979 (Report No. 50-352/79-07)

Areas Inspected:

Routine, unannounced inspection by regional based inspector

of work activities and records associated with safety related piping.

The

inspector also performed a plant tour inspection. The Unit 1 inspection

involved 23 inspector-hours on site by one regional based inspector.

Results: Of the two areas inspected, no items of noncompliance were identified

in one area, two apparent items of noncompliance were identified in one area

(Infractions - (1) Failure to follow design requirement for welding of safety

related pipe restraint, Paragraph 4; (2) Failure to follow design specificationc

~

requirement for the welding of temporary attachments to containment liner

Paragraph 4).

Unit 2 Inspection on July 5, 6, and 9, 1979 (Report No. 50-353/79-07)

Areas Inspected:

Routine, unannounced inspection by regional based inspector.

The inspector performed a plant tour inspection.

The Unit 2 inspection involved

2 inspector-hours on site by one regional based inspector.

.

Results:

No items of noncompliance were identified.

138i

320

Region I Form 12

(Rev. April 77)

7911210

.

DETAILS

1.

Persons Contacted

Philadelphia Electric Company

  • D. Clohecy, QA Engineer
  • J. Corcoran, Field QA Branch Head

D. DiPaolo, yA Engineer

J. Evans, QA Engineer

  • J. Fedick, Construction Engineer
  • S. Genca, Assistant QA Engineer
  • D. Marascio, QA Engineer

Bechtel Power Corporation

  • T. Altum, Lead Field Welding Engineer
  • B. Dragon, QA Engineer
  • T. Fallon, Assistant Project Field QC Engineer
  • H. Foster, Assistant Project Field QC Engineer
  • R. French, Field Contracts Administrator
  • G. Harper, Subcontracts Field Engineer
  • M. Jan, Area Engineer
  • G. Kelly, QA Engineer
  • E. Klossin, Project QA Engineer
  • R. Leingang, Assistant Project Field Engineer

M. Norman, Assistant Lead QC Weld Engineer

  • L. Pons, Resident Engineer
  • J. Reiney, Project Construction Manager
  • R. Sevo, Lead OA Engineer

L. Vernon, QC Weld Engineer

T. Waters, Lead QC Weld Engineer

  • R. Zittel,. Area #1 Superintendent
  • Denotes those in attendance at the Exit Interview

2.

Licensee Action on Previous Inspection Findings

(Closed) Noncompliance (352/79-02-05):

Failure to properly store safety

related stainless steel pipe spools in laydown area.

The inspector reviewed

four licensee audit reports, Nos. P-121, P-122, P-123, and P-127, which

reported the results of the audits the licensee conducted on pipe storage

in the laydown area and also in the plant buildings.

The audit results

were properly documented and timely corrective action had been taken.

The

inspector inspected the laydown area for storage of safety related stainless

steel pipe spools.

The inspector noted that nine stainless steel spools

were not stored in accordance with the requirements of the storage procedure.

138i

Q1

.

3

The licensee identified these spools (DCA-201-1-1 thru DCA-201-1-6 and DCA-

101-1-2,

-3, and -4), as the surplus spools mentioned in their audit

report P-127.

The inspector verified that these spools were surplused;

however, the Bechtel memo which was dated June 12, 1979, stated that the

above spools can be used in whole or canibalized for use in rework of other

systems if the material is compatible with that system. The inspector

informed the licensee that since these pipe spools may be used in a safety

related system, they have to be stored in accordance with the requirements

of the Bechtel Storage Procedure.

Corrective action was taken and the nine

pipe spools were stored in accordance with the Bechtel Job Rule G-8 Require-

ment.

No items of noncompliance were identified.

3.

Plant Tour (Units 1 and 2)

The inspector toured the Units 1 and 2 containment and reactor buildings

observing work in-progress, inplace storage practices, area cleanliness,

and completed work. The inspector examined work items for any obvious

defects or noncompliance with Regulatory Requirements.

The following item

was identified during this plant tour inspection:

a.

The inspector noted a partial weld buildup on a safety related pipe

located in Area 15 at elevation 181', which was adjacent to Hanger

HBB-ll 7-ill 8.

The licensee stated that a nonconformance report, No.

3615, was issued for this weld.

It appears that this weld repair was

made without Bechtel Quality Control being notified.

The surface

condition prior to the repair and the depth of the repair are unknown.

The licensee has issued a Quality Action Request (QAR #F-128) to

Bechtel stating that this is a recurrence of unauthorized welding and

that if corrective action is not effective, a Bechtel Management

Corrective Action may be warranted.

The inspector informed the licensee

that this item is considered unresolved pending review of Bechtel's

corrective action regarding this matter (352/79-07-01).

4.

Reactor Coolant Pressure Boundary - Observation of Work (Unit 1)

The following listed activities were observed to determine that the require-

ments of selected portions of the ASME III and IX Codes, the Bechtel 0A

Manual (ASME Section III) and the Bechtel Specifications P-319 (Revision

7), P-301 (Revision 6), and P-322 (Revision 1) had been adhered to:

1381

22

.

.

4

Primary Steam and Feedwater Piping Restraints

a.

The inspector inspected pipe restraint weld joints in various stages

of completion.

The restraints inspected were identified as PR-9, PR-

42, PR-47, PR-12, PR-43, PR-il, and PR-44.

The following items were

found during this inspection:

-

(1) A backing bar is used when welding the two circumferential pieces

of a restraint together. The inspector notes that the backing

bar is attached to the restraint ,by various amounts of weld,

since there are no requirements for the amount of weld to be used.

There are instances where the backing bar is either tack welded

on both edges, or one edge is welded to the restraint.

The

inspector also could not find in various documents any acceptance

criteria for what is the allowable gap between the backing bar

and restraint. The inspector questioned the QC engineer what

te used i v an acceptance criteria.

He stated that his criteria

was " tight against the restraint." The inspector informed the

licensee this is considered unresolved pending review of their

evaluation of this situation (352/79-07-02).

(2)

The inspector also noted during his inspection of the pipe restraints

that the restraints supplied by Chicago Bridge and Iron had a

cope or access hole where the horizontal and vertical weld joints

coincide.

This was apparently done to assure that a full penetra-

tion weld is obtained. The Mississippi Valley Company supplied

restraints do not have an access hole at the weld joint junction,

therefore, it is questionable that the required full penetration

weld can be obtained. The licensee stated that this item will be

evaluated.

The inspector informed the licensee this item is

considered unresolved pending review of their evaluation (352/79-

07-03).

(3)

During the inspection of completed restraint, identified as PR-9,

the inspector noted that the backing bar was welded on one edge

only and was warped. The completed weld joint (horizontal) was

approximately 1/4 of an inch misaligned.

The weld joint was

accepted by QC engineer on April 9, 1979.

A review of Drawing C-

292, Revision 8, indicated that a Field Change Request No. C-

5542F was issued on April 9,1979 to provide for fitup tolerances

for restraints.

This request was approved as Field Design Change

No. 5 and it requires that when there is a misalignment (1/2"

maximum) the backing bar is te be removed after one side of weld

joint has been welded and a sr. to one taper shall be provided at

the weld joint where the backing bar was. This was not done.

This is contrary to the Limerick Procedure PSP-G-6.1, Revision 2,

1381 m

.

.

5

which requires a new inspection for additional work to be accom-

plished to completed work due to an engineering change. The

licensee was informed that this was an item of noncompliance

(352/79-07-04).

(4) De ing the above inspection of restraints, the inspector also

noted that temporary brackets (used for construction aids) were

welded to the containment to temporarily support or align piping.

The inspector asked to see documentation for these temporary

welds to determine if they were being controlled. The inspector

found that these welds were treated as nonsafety related, therefore,

Quality Control was not involved and weld history information was

not documented.

Several of the welds were made on liner penetra-

tions (penetrations X9A and X98), which were 1-1/2 inches thick,

therefore, requiring a minimum preheat of 2000F.

The licensee was

informed that this was contrary to the requirements of Bechtel

Specification C-2, which require that weldina of temporary attach-

ments be controlled (use of qualified welders and proce_ures,

d

.

preheat, and nondestructive examination of liner after removal

of temporary attachment.), and that this is an item of noncompliance

(352/79-07-05).

5.

Reactor Coolant Pressure Boundary - Review of Records (Unit 1)

A review of two pipe spool Quality Assurance Document packages was performed

to verify compliance with Specification P-312, the ASME III Ccde, and

Regulatory Requirements.

The following pipe spool document packages were

reviewed:

Pipe Spool

Size

Nuclear Class

Material

DCA-105-1-3

20"

1

304 Stainless Steel

DCA-105-1-4

20"

1

304 Stainless Steel

The documents reviewed consisted of the material test reports, shop fabrica-

tion and inspection records.

No items of noncompliance were identified.

6.

Unresolved Items

Unresolved items are matters about which more information is required in

order to ascertain whether they are acceptable items, items of noncompliance,

or deviations. Three unresolved items disclosed during this inspection are

discussed in Paragraphs 3 and 4.

1381

324

.

.

6

7.

Exit Interview

The inspector met with licensee representatives (denoted in Paragraph 1) at

the conclusion of the inspectio. cn July 9, 1979.

The inspector summarized

the purpose and scope of the inspection and the findings.

1381

325