ML19260A274
| ML19260A274 | |
| Person / Time | |
|---|---|
| Site: | Byron |
| Issue date: | 10/12/1979 |
| From: | Karman M NRC OFFICE OF THE EXECUTIVE LEGAL DIRECTOR (OELD) |
| To: | Callihan A, Cole R, Mark Miller Atomic Safety and Licensing Board Panel |
| References | |
| NUDOCS 7911080421 | |
| Download: ML19260A274 (2) | |
Text
q T
g atog o
UNITED STATES 4
g g
NUCLEAR REGULATORY COMMISSION e
WASHINGTON, D. C. 20555
/
October 12, 1973 Marshall E. Miller, Esq., Chairman Dr. A. Dixon Callihan Atomic Safety and Licensing Board Panel Union Carbide Corporation U. S. Nuclear Regulatory Comission P. O. Box Y Washington. D. C.
20555 Oak Ridge, Tennessee 37830 Dr. Richard F. Cole Atomic Safety and Licensing Board Panel U. S. Nuclear Regulatory Commission Washington, D. C.
20555 In the Matte: of Comonwealth Edison Company IByron Station, Units 1 and 2)
Docket Nos. 50-454 & 50-455 Gentlemen:
In accordance with the Licensing Board's request for a progress report on continuing negotiations between Applicant, Intervenors and NRC Staff re-garding contentions in the Byron 1-2 operating license proceeding, the following report is submitted with the consent of all parties:
1.
On September 25, 1979, counsel for Staff and Applicant met with counsel and individual members of DAARE/ SAFE in DeKalb, Illinois.
Dr'ftsmanship and substance of Intervenors' conten-tions was disecssed. The outcome of that meeting was that Intervenors would obtain technical assistance, consult with counsel, and forward revised proposed contentions to Applicant and Staff.
Further action by the parties will await receipt of those contentions, which are expected to be served by mail na later than October 22, 1979.
2.
On September L6,1979, counsel for Applicant and Staff met with Myron Charry, Esq., and individual representatives of the League o' Women Voters of Rockford, Illinois, in Chicago, Illinois. Draftsmanship and substance of Intervenor's pro-posed contentions was similarly discussed at this meeting.
The outcome of this meeting was that Applicant would submit to Intervenor and Staff a detailed statement of position on Intervenor's present proposed contentions. This document was mailed on October 9,1979. Subsequently, Staff will furnish to Intervenors its statement of position on the proposed con-tentions. Thereafter, 'ntervenors will submit a revised state-meint of pronosed contentions to Applicant and Staff, which is expected no iater than November ?, 1979.
1297 322 ton oso Lf2l
s
.. 3.
After receipt of each Intervenors' revised submission of proposed contentions, an attempt vill be made to arrive at a stipulation of contentions for discovery and litigation with each Intervenor.
4.
The parties propose to notify the Licensing Board of the progress of their ongoing efforts 45 days from the date of this letter--November 27, 1979.
It is hoped that the parties will have concluded all negotiations by this time.
Sincerely, i
J Myro Karman Cou#sel for NRC Staff cc:
Paul M. Murphy, Esq.
Mrs. Phillip B. Johnson Jerome Hughey, Esq.
Dr. t$ruce von Zellen Ms. Beth L. Galbreath Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Appeal Board Panel Docketing and Service Section 1297 323
.