ML19259D098

From kanterella
Jump to navigation Jump to search
Forwards IE Bulletin 79-14,Suppl 1, Seismic Analysis for As-Built Safety-Related Piping Sys. Action Required
ML19259D098
Person / Time
Site: Marble Hill
Issue date: 08/15/1979
From: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Coughlin J
PSI ENERGY, INC. A/K/A PUBLIC SERVICE CO. OF INDIANA
References
NUDOCS 7908300297
Download: ML19259D098 (1)


Text

' e n o

,'o, f((

va

[

UNITED STATES 8i NUCLEAR REGULATORY COMMISSION n

$(

c.E REGION lli o,

[

799 ROOSEVELT ROAD r

'.%/

GLEN ELLYN, ILLINOIS 60137 o

  • ...+

$G1b Docket No. 5' -546 5~

Docket No.51-547 fPublicServiceofIndiana ATTN:

Dr. James Coughlin Vice President, Nuclear 1000 East Main Street Plainfield, IN 46168 Gentlemen:

The enclosed supplement to IE Bulletin No. 79-14 is forwarded to you to provide added guidance on the intent of the Bulletin.

If you desire additional information regarding this matter, please contact this office.

Sincerely, 0-

[JamesG.Keppler U

Director

Enclosure:

Supplement IE Bulletin No. 79-14 cc w/ encl:

Mr. R. M. Brown, Construction Project Superintendent Central Files Director, NRR/DPM Director, NRR/ DOR PDR Local PDR NSIC TIC LeBoeuf, Lamb, Leiby & MacRae 2107 178 79083009 %

SSINS:

6820 g

Accession No:

M 000364 6

,8 UNITED STATES NUCLEAR REGULATORY COMMISSION 0FFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.

20555 -

5 i

August 15, 1979 s

C Supplement IE Bulletin No. 79-14 SEISMIC ANALYSlo FOR AS-BUILT SAFETY-RELATED PIPING SYSTEMS Discription of Circumstances:

IE Bulletin No. 79-14 was issued on July 2,1979 and revised on July 18, 1979.

The bulletin requested licensees to take certain actions to verify that seismic analyses are applicable to as-built plants. This supplement to the bulletin provides additional guidance and definition of Action Items 2, 3, and 4.

To comply with the requests in IE Bulletin 79-14, it will be necessary for licensees to do the following:

2.

Inspect Part of the Accessible Piping For each system selected by the licensee in accordance with Item 2 of the Bulletin, the licensee is expected to verify by physical inspection, to the extent pri.cticable, that the inspection elements meet the acceptance criter'.a.

In performing these inspectons, the licen'ee is expected to use measuring techniques of sufficient accuracy to delonstrate that acceptance criteria are met.

Where inspection ele nts important to the seismic analysis cannot be viewed because of the: ~1 insulation or location of the piping, the licensee is expected to remove thermal insulation or provide access. Where physical inspection is not practicable, e.g., for valve weights and materials of construction, the license is expected to verify conformance by inspection of quality assurance records.

If a nonconformance is found, the licensee is expected in accordance with Item 4 of the Bulletin to perform an evaluation of the significance of the nonconformance as rapidly as possible to determine whether or not the operability of the system might be jeopardized during a safe shutdown earthquake as defined in the Regulations. This evaluation is expected to be done in two phases involving an initial engineering judgement (within 2 days), followed by an analytical engineering evaluation (within 30 days).

Where either phase of the evaluation shows that system operability is in jeopardy, the licensee is expected to meet the applicable technical specification action statement and complete the inspections T

required by Item 2 and 3 of the Bulletin as soon as possible.

The licensee

~ @