A g# "8%
UNITED STATES Mgg NUCLEAR REGULATORY COMMISSION y
{
j REGION I e
c
$31 PARK AVENUE KING OF PRUS$1 A, PENNSYt.,VANI A 19406 Docket No. 70-33 MR9 US Texas Instruments Incorporated ATTN: Mr. Daniel H. Conroy Manufacturing Manager, Metal Systems Department 34 Forest Street Attleboro, Massachusetts 02703 Gentlemen:
Subject:
Inspection 70-33/79-03 This refers to the inspection conducted by Mr. W. W. Kinney of this office on March 5-8, 1979, of activities authorized by NRC License No. SNM-23 and to the discussions of our findings held by Mr. Kinney with yourself and others of your staff at the conclusion of the inspection, and to a subsequent telephone discussion between Mr. Sherman of your staff and Mr. Kinney on March 15, 1979.
Areas examined during this inspection are described in the Office of Inspection and Enforcement Inspection Report which is enclosed with this letter. Within these areas, the inspection consisted of selective examinations of procedures and representative records, interviews with personnel, and observations by the inspector.
Our inspector also verified the steps you have taken to correct the item of noncompliance brought to your attention in a letter dated December 6, 1978. We have no further questions regarding your action at this time.
Within the scope of this inspection, no items of noncompliance were observed.
In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2, Title 10, Code of Federal Regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public Document Room.
If this report contains any infomation that you (or your con-tractor) believe to be proprietary, it is necessary that you make a 2282 174 7906140(o39, h
E3 0
Texas Instruments Inc.
2 written application within 20 days to this office to withhold such information from public disclosure.
Any such application must be accompanied by an affidavit executed by the owner of the information, which identifies the document or part sought to be withheld, and which contains a statement of reasons which addresses with specificity the items which will be considered by the Commission as listed in subparagraph (b)(4) of Section 2.790.
The information sought to be withheld shall be incorporated as far as possible into a separate part of the affidavit.
If we do not hear from you in this regard within the specified period, the report will be placed in the Public Document Room.
No reply to this letter is required; however, should you have any questions concerning this inspection, we will be pleased to discuss them with you.
Sincerely, George H. Smith, Chief /M Fuel Facility and fiate als Safety Branch
Enclosure:
Office of Inspection and Enforcement Inspection Report Number 70-33/79-03 cc w/ encl:
W. George, Assistant Vice President and Manager, Metallurgical flaterials Division F. L. Sherman, Manager, HFIR Project 2282 175