'l E
Ii, t USHRC REG E' ~
3Ti AtJTt Gr Vepco i9 IM I4 May 10, 1979 Mr. James P. O'Reilly, Director Serial No. 344 Office of Inspection & Enforcement PSE&C/JMM:mac:wan U. S. Nuclear Regulatory Commission Region II Docket N
. 50-339 101 Marietta Street, Suite 3100 50-404 Atlanta, Georgia 30303 g
Dear Mr. O'Reilly:
We have reviewed IE Bulletin No. 79-03 dated March 12, 1979, forwarded by NRC letter of March 12, 1979.
Due to the extensive records review required for compliance with IE Bulletin No. 79-03, Vepco will require an additional 30 days minimum to reply.
It is our intention, therefore, to reply to IE Bulletin No. 79-03 by June 11, 1979.
Very truly yours, b.D? %d?6fAhf f~
Sam C. Brown, Jr.
Senior Vice President - Power Station Engineering and Construction cc: Mr. John G. Davis, Acting Director Office of Inspection & Enforcement Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation 2279 228 E
a 7906140 t/67 '