Responds to NRC 790105 Ltr Re Violations Noted in IE Insp Repts 50-373/78-28 & 50-374/78-20.Corrective Actions:Record in Question Was for Info Only & Was Not Required.Weld Integrity Verified for Completed Weld
ML19259B723
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 02/05/1979
From: Reed C
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML19259B721 List:
References
NUDOCS 7903130608
Download: ML19259B723 (3)


Text

Commonwealth Edison Cne First National Plaza. Chicago. lihnots Address Reply to Post Office Box 767 Chicago. Illinois 60690 February 5, 1979 Mr. James G. Keppler, Director Directorate of Inspection and Enforcement - Region III U.S. Nuclear Regulatory Commission -

799 Roosevelt Road Glen Ellyn,' Illinois 60137

Subject:

LaSalle County Station Units 1 and 2 Response to IE Inspection Report Nos.

60-373/78- b nd 50-374/78-20 NRC Pocket Nos. 50-373 and 50-374 Reference (a): R. F. Heishman letter to B. Lee, Jr.

dated January 5, 1979

Dear Mr. Keppler:

The following is in response to an inspection conducted by Mr. C. M. Erb on October 31 through November 3, 1978 of activities at LaSalle County Station. Reference (a) indicated that certain activities appeared to be in noncompliance .Jith NRC requirements. These requirements are addressed in the enclosure to this letter.

Please refer any questions you may ha7e on this matter to this office.

Very truly yours,

( _ _ ,

Cordell Reed Assistant Vice-President enclosure 28 819D9 7003130 649%

Commonwealth Edison FB. 21. 1979 Company We expect to find in the site files, records of the grindout and repair or other records documenting disposition of your acceptance of the ASME Code unacceptable discontinuity. We will examine your corrective action during a future inspection.

Your cooperation with us is appreciated.

Sincerely,

% AMh' Caston Fiorelli, Chief Reactor Construction and Engineering Suppott Branch cc: Mr. L. J. Burke, Site Project Superintendent Mr, T. E. Quaka, Quality Assurance Supervisor Mr. Cordell Reed, Assistant Vice President cc w/ltr dtd 2/5/79:

Central Files Reproduction Unit NRC 20b PDR Local PDR NSIC s' TIC Mr. Dean Hansell, Office of Assistant Attorney General