{{#Wiki_filter:? $ . . UNIT E D STATES [[, 4,k NUCLEAR REGULATORY COMMISSION f 1, .' REGloN HI p - 799 ROOSEVELT ROAD ' , GLE N E LLY N, ILLINots 60137
% -J., - j .
- ..*
JAN 2 3 j79 ~ ~ Docket No. 50-454 Docket No. 50-455 Docket No. 50-456 Docket No. 50-457 Commonwealth Edison Company ATTN: Mr. Byron Lee, Jr. Vice President Post Office Box 767 Chicago, IL 60690 , Gentlemen: This refers to the inspection conducted by Messrs. J. E. Konklin and P. A. Barrett of this of fice on December 14, 1978 at yout corporate offices relating to activities at Byron Nuclear Generating Station, Units 1 and 2, authorized by NRC Construction Permits No. CPPR-130 and No. CPPR-131, and Braidwood Nuclear Generating Station, Units 1 and 2, authorized by NRC Construction Permits No. CPPR-132 and No. CPPR-133, and to the discussion of our findings with Mr. Shewski and others of your staff at the conclusion of the inspection. The enclosed copy of our inspection report identifies areas examined during the inspection. Within these areas, the inspection consisted of a selective examination of procedures and representative records, obser- vations, and interviews with personnel. No items of noncompliance with NRC requirements were identified during the course of this inspection. In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public Document Room, except as follows. If this report contains information that you or your contractors believe to be proprietary, you must apply in writing to this office, within twenty days of your receipt of this letter, to withhold such information from public disclosure. The application must include a full statement of the reasons for which the information is considered proprietary, and should be prepared so that proprietary information identified in the application is contained in an enclosure to the application. . 7 9 0 313 0 4 Go
. . , JKN 2 t 379 ' Cornonwealth Edison 2- - Cotapany We vill gladly disc ss any questions you have concerning this inspec- tion. . . . Sincerely, R. F. Beishman, Chief Reactor Construction and Engineering Support Branch Enclosure: IE Inspection Reports No. 50-454/78-11;; No. 50-455/78-11; No. 50-456/78-14; and No. 50-457/78-14. cc w/ encl: Gunnar Sorensen, Station Superintendent, Byron Richard Cosaro, Station .
Superintendent, Braidwood Central Files Reproduction Unit NRC 20b PDR Local PDR NSIC TIC Mr. Dean Hansell, Office of Attorney General . 5 RIII 7 I _I_ ___________ _ Il _____. .____________. _ _R,}_I,I ' _,,,, _,, S , ,___, __ _ _ _ , orricr> {?.U_____________ . _ _D7_e_ ,, ,,,,, ,, ,p a_r_r_ _ _t_q ,, _ _ _ _ _ _ _ p_ J_a_d_ _ _ __ _) _ M h m .___. ' ' r .____________. suRnau ___ _ _1_ /_2,2 /_7_9_ _ _ _ _ _ _ _ D^ * __________________ ________________._-______--__-- _____,___________ _________________ NRC Form 3108 (R nI)(178) NRCM O240 .u. s novtahmasset ram?I'*0 0'recai nors-rss ent }}