ML19259B298

From kanterella
Jump to navigation Jump to search
Preliminary Answers by Intervenors to Interrogatories Submitted by Applicant.Interrogatories Pertain to Site Selection.Certificate of Svc Encl
ML19259B298
Person / Time
Site: Perkins  Duke Energy icon.png
Issue date: 01/02/1979
From: Pfefferkorn W
PFEFFERKORN & COOLEY, P.A.
To:
References
NUDOCS 7901260031
Download: ML19259B298 (7)


Text

2* I q

$p Ef gf .f NRC PUBLIC D% g bfh$

UNITED STATES OF AMERICA &

NUCLEAR REGULATORY COMMISSION la

) Docket Nos. STN STN50-488 50-489 In the Matter of ) STN 50-490

)

DUKE POWER COMPANY )

)

(Perkins Nuclear Station, )

Units 1, 2 and 3) )

PRELIMINARY ANSWERS TO INTERROGATORIES AND REQUESTS TO PRODUCE _

atories NOW COME the Intervenors regarding the Interrog d do hereby state and Requests to Produce of the Applicant an t opportunity and ii that the Intervenors have not had suff i s andc en Requests to time to fully respond to the Interrogator eh n such additional Produce and will supplement these Answers w e On account of information and other matters become h Intervenors available.

have been the holidays and the shortness of time, te tions at this time unable to answer many aspects of these ques i on the basis of its own and are still in the process of prepar ng n review of Interrogatories to Applicant as well as its ow licant to determine information which it has received from the App t for January 29, how it will proceed in the hearing which is se 1979. f the 1 Intervenors understand that at least two o issues are whether there are other obviously superior sites d whether the NRC Staf f the Perkins site for a nuclear station danalternative sites.

has adequately become informed and evaluate h se questions and There may be other issues connected with t e 790126001/

6

there is certainly a generic issue which the Intervenors are in the process of studying at this time.

2. The preliminary indication of Intervenors' under-standing of at least two of the issues is based upon the pleadings and briefs which were filed in the spring and summer of 1978 and the information which was filed in the summer and fall of 1978 by the Applicant and by the NRC Staff. As pointed out above, the Intervenors have not completed their research and anaylsis and therefore it may well be that other issues will emerge, or that the issues will be framed in a different way.
3. At this time it is the Intervenors' position that there are other superior sites to the Perkins site and that the NRC Staff has not done an adequate j ob of either informing itself or in evaluating and analyzing the alternative sites.
4. The Intervenors' basis for this has been set out in its filing of December 22nd to some extent and the Intervenors are now in the process of developing fully its evider.ce for the hearing on January 29, 1979, which will set out that basis for its position. The Intervenors are reviewing information obtained from the applicant and information in the file of this case, as well as other information in order to support its position.
5. In the an.awer to the previous questions, Intervenors mentioned the filing in this proceeding as well as information which it received from the Applicant which Intervenors believe will support Intervenors' position. The Intervenors are in the process of organizing this material and cannot at this time list specifically which portions of this material it is relying on at the present time.
6. The Intervenors are now attempting to contact various experts and to obtain additional information in preparation to prefile testimony in regard to the hearing on January 29, 1979.
7. The Intervenors are in the process of attempting to contact experts and laymen throughout north Carolina in regard to the alternate site questions. Intervenors are making contacts with people at various schools, colleges and universities and at other institutions in attempt to obtain help and guidance on factual and analytical questions.
8. As of this time, the Intervenors have no knowledge that any documents have been prepared, research undertaken or studies conducted in regard to its attempts to obtain the help mentioned in the previous questions.
9. Yes. Intervenors intend to prefile testimony, present witnesses and exhibits and to cross-examine and otherwise fully participate in the hearing.
10. Yes. At this time, Intervencrs do not know who will sponsor such testimony.
11. See answer to No. 10.
12. See answer to No. 10.
13. Yes. The Intervenors are in the process of pre-paring its information and anaylsis in regard to its position that sites obviously superior to the Perkins site exist for the construction and operation of a nuclear power plant similar to Perkins. When this work is completed, Intervenors will file the results of this work.
14. Intervenors are now working on the basis for its conclusion; but as mentioned earlier, it has previously pointed out some of the relevent information which it has received and which it believes will be useful in basing such conclusions, and the sources of this information are set out in answers to previous Interrogatories.
15. The Intervenors are working on its evaluation and when it is completed they will give what they consider to be the most important criterion with respect to alternate site selection. Intervenors will also give the basis for such criterion selection.
16. When the Intervenors have completed their work they will also give other criteria which support their conclusions.
17. Intervenors have visited various sites, including but not limited to the Lake Norman sites. Certain representatives of the Tntervenors have visited other sites and the Intervenors are now in the process of getting together all of its information of 4. sited sites and will be furnishing this information as soon as it has obtained all of it.
18. Intervenors have always considered that the Perkins site is not a viable site. Therefore, many sites have always been obviously superior to the Perkins site which has always been considered by the Intervenors, and many other persons, agencies, institutions and companies to be a defective and woefully inadequate site for a nuclear plant. The Intervenors are in the process of determining when other sites were considered specifically as viable alternatives. We will supplement this answer when such information is available.
19. Yes.
a. The Intervenors have not completed their anaylsis which will allow it to answer in a full and complete way a - e of this question, but will do so shortly in a complete manner.
20. Yes. The Intervenors have previously in its filing of November 22nd dealt with some of the issues raised in subquestions a - e and when the Intervenors complete shortly their work on this matter they will supplement their answer to this question and answer fully questions a - e.
21. Yes. See answers to Nos. 19 and 20 above.
22. Intervenors have contacted various State, Federal and local officials with regard to the consideration of sites other than Perkins. These contacts have been so numerous and for over such a long period of time it would not be possible for Intervenors to give a list of such contacts.
23. Yes. They remain active.
24. The Intervenors have discussed and had meetings in regard to the issues under-consideration many times--over the past several years. Intervenors do not now know the dates of such meetings and discussions.
25. The Intervenors are aware of the position which they take in response to these Interrogatories.
26. David Springer and Mary Davis.
27. Yes. Intervenors have attended numerous local, State and Federal meetings over the past several years in regard to the subject of alternate sites in general. It would not be possible to list the dates and places of such meetings.
28. Yes. See answer to No. 27 above.
29. Yes. See answer to No. 27 above. The types of meetings which have been attended over the past several years have not limited themselves in the manner set out by questions No. 27, 28 and 29. At most of these meetings all three of the issues raised in these three questions have been brought up in one way or the other.
30. The Intervenors have attended various meetings, including hearings of this Board, which presented the question of power plant siting. As to whether the authorities presented in these hearings and other hearings by State agencies were knowledgeable is a question which has not been finally decided and indeed is perhaps the purpose of this re-opened hearing on January 29, 1979. Therefore, Intervenors would not concede that certain authorities presented up to this date are in fact knowledgeable, but hope to present such knowledgeable authorities at the hearing on January 29, 1979.

This the 2nd day of January, 1979.

Sworn to and subscribed WilliSE G. Pfefferkofn ' g F before me this 2nd day of y January, 1979.

11k ]_1.

Notary Publ'It:

1 f

My commission expires: February 7, 1980

CERTIFICATE OF SERVICE I he.reby certify that copies of Preliminary Answers to Interrogatories and Requests to Produce in the above-captioned matter have been served on the2nd following by deposit in the United States mail this day of January , 19 79 .

Elizabeth S. Bowers Charles A. Barth, Esq.

Chairman, Atomic Safety Counsel for NRC Regulatory Staff and Licensing Board Office of the Executive Legal U.S. Nuclear Regulatory Director Commission U.S. Nuclear Regulatory Washington, D.C. 20555 Commission Washington, D.C. 20555 Dr. Donald P. deSylva Associate Professor of William A. Raney, Jr., Esq.

Marine Science Special Deputy Attorney General Rosenstiel School of Marine State of North Carolina and Atmospheric Science Department of Justice University of Miami Post Office Box 629 Miami, Florida 33149 Raleigh, North Carolina 27602 Dr. Walter H. Jordan William L. Porter, Esq.

881 West Outer Drive Associate General Counsel Oak Ridge, Tennessee 37830 Duke Power Company Post Office Box 2178 Chairman, Atomic Safety Charlotte, North Carolina 28242 and Licensing Board Panel U.S. Nuclear Regulatory Mr. Chase R. Stephens Commission Docketing and Service Section Washington, D.C. 20555 Office of the Secretary U.S. Nuclear Regulatory Chairman, Atomic Safety and Commission Licensing Appeal Board Washington, D.C. 20555 U.S. Nuclear Regulatory Commission Mr. J. Michael McGarry, III Washington, D.C. 20555 Debevoise and Liberman 700 Shoreham Building 806 Fifteenth Street Washington, C. Q005 WilTiam G. Pfefferk6rn Attorney for IntervenorsV '[/ y//

PFEFFERKORN & COOLEY, P.A, Post Office Dox 43 Winston-Salem, N.C. 27102 Telephone: (919) 725-0251