December 31, 1979 In Reply Refer To:
RIV Docket No..0-498/499 Houston Lighting and Power Company ATTN:
Mr. G. W. Oprea Executive Vice President P. O. Box 1700 Houston, Texas 77001 Gentlemen:
This refers to a special inspection at the South Texas construction site during the past six weeks, meetings with you and members of your staff on December 21 and 28, 1979, and to your letter dated December 28, 1979.
As a result of our spec.a1 inspection effort, a number of problems associ-ated with the placement of concrete were identified and discussed with you.
Consequently, we understand that you:
1.
Have initiated a Nine-Point Corrective Action Program to elimate problems connected with concrete placement and inspection activities.
(The Nine-Point Corrective Action Program is contained in your December 28 letter.)
2.
Plan to limit safety related concrete placements to placements classified as Non-Complex until such time as the Nine-Point Corrective Act on Program has been fully implemented.
3.
Plan to notify the Region IV Office when you have implemented the Nine-Point Corrective Action Program and such notification is to occur at least 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> prior to the resumption of safety rc__ted, complex concrete placement to permit NRC verification of satisfactory implementation of the Corrective Action Program.
If your understanding of this matter is inconsistent with the above, please contact this office famediately.
Sincerely,
=
u
/
f"
/
- V
$9c, L
- i A'-,"
t xy g
i Karl V. Seyfrit-Director s'