Responds to NRC 791121 Ltr Re Violations Noted in IE Insp Repts 50-445/79-27 & 50-446/79-26.Corrective Actions: Revised & Deleted Procedures to Reflect Reassignment of Qa/Qc Responsibilities
ML19257C218
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 12/21/1979
From: Gary R
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML19257C216 List:
References
NUDOCS 8001250281
Download: ML19257C218 (3)


Text

. .

TEXAS UTILITIES GENERATING COMPANY 2001 BRYAN TOWER D4tLAS.TEXAB 75201 a.1 om December 21, 1979

".'YJ' .?' :'.*?' ' TXX-3081 Mr. W. C. Seidle, Chief Reactor Construction and Engineering Support Branch U.S. Nuclear Regulctory Commission Office of Inspection & Enforcement 611 Ryan Plaza Dr., Suite 1000 Docket Nos. 50-445/79-27 Arlington, Texas 76012 50-446/79-26 COMANCHE PEAK STEAM ELECTRIC STATION 1981-83 2000 MW INSTALLATION RESPONSE TO NRC NOTICE OF VIOLATION DATED NOVEMBER 21, 1979 INSPECTION REPORT NOS. 79-27, 79-26 DOCKET N05. 50-445 & 50-446 FILE N0. 10130

Dear Mr. Seidle:

We have reviewed the report dated November 21, 1979 on the inspection conducted by your resident inspector, Mr. R. G. Taylor, of the activities authorized by NRC Construction Permits No. CPPR-126 and 127 for the Comanche Peak facility. We have responded to the findings listed in Appendix A of that report.

To aid in the understanding of our response, we have repeated the require-ment and your findings followed by our corrective action.

We believe the attached information to be responsive to the Inspector's findings. If you have any questions, please advise.

Very truly yours, kl R. . Gary RJG:df Attachment 1808 277 8001250 18l

Inspection Report Nos. 79-27, 79-25 TXX-3081 Page 2 Appendix A NOTICE OF VIOLATION Based on results of the NRC inspection conducted on November 15, 1979, it appears that certain of your activities were not conducted in full compliance with the conditions of your NRC Construction Permits No. CPPR-126 and 127 as indicated below:

Failure to Update Procedures 10 CFR 50, Appendix B, Criterion V states in part, " Activities affecting quality shall be preso-ibed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accom-plished in accordance with these instructions, procedures or drawings."

Contrary to the above:

Review of site Quality Assurance procedures reveals that some are not of a type appropriate to the circumstances and that certain activities affecting quality are not accomplished in accordance with existing procedures in that the following procedures, as a minimum, are obsolete since they no longer represent the organization, functional responsi-bilities and/or method of operation as appropriate:

1. CP-QP-3.0, Revision 0, "CPSES Site Quality Assurance Organization"
2. Q1-CP-11.0-AE, Revision 0, " Deviations to Quality Assurance / Quality Control Activities"
3. CP-QAP-1.1, Revision 0, "B&R Site QA Organization"
4. CP-QAP-2.2, Revision 0, "Stop Work"
5. CP-QAP-6.1, Revision 0, " Distribution and Control of Quality Assurance Procedures, Instructions and Manuals"
6. CP-QAP-10.3, Revision 2. "QC Surveillance of Welding Activities and Materials"
7. CP-QAP-15.2, Revision 0, " Handling of Potential Reportable Deficiencies" k808278 .

Inspection Report Nos. 79-27, 79-26 TXX-3081 Page 3

8. CP-QAP-17.1, Revision 1, " Management of Quality Assurance Records"
9. CP-QAP-18.2, Revision 2, " Site Surveillance" This is an infraction.

Corrective Steps Which Have Been Taken and Results Achieved Corrective actions have included revision or deletion of the listed procedures as well as others which are no longer required or were in need of revision to reflect re-assignment of responsibilities within the site QA/QC organization.

Corrective Steps Which Have Been or Will Be Taken to Avoid Further Noncompliance Assignments for review and necessary revision of the listed procedures and others had been made and documented prior to the NRC Inspection of November 15, 1979, but scheduled completion dates were not achieved. Preventive measures will therefore consist of stronger follow through on staff assignments to assure completion in a timely manner.

Date of Full Compliance Corrective and preventive measures are currently complete.