Interim Deficiency Rept Re Omission of Class B Fill Waterstops.Double Waterstops Installed at Eight Locations & Single Waterstops Installed at Seven Locations.Final Rept Will Be Forwarded by 800229
ML19257B404
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 01/07/1980
From: Davidson D
CLEVELAND ELECTRIC ILLUMINATING CO.
To:
References
NUDOCS 8001150668
Download: ML19257B404 (1)


Text

'

ILLUMINADNG SLOG. e PUBLIC SQUARE e CLEVELAND. oHto 44101 e TELEPHONE (216) 6231350 e 'A All ADDRESS - P O. BCx 5000 Dalwyn R. Davidson Ic7(($ctn%cmoco4sinuer.cs January 7, 1980 Mr. James G. Keppler Director, Region III Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 RE:

Perry Nuclear Power Plant Interim Report on Omission of Class "B" Fill Waterstops

Dear Mr. Keppler:

This letter constitutes the Interim Report as required by 10CFR30.55(e) on the omission of the Class "B" Fill waterstops. The condition was reported to Region III by Mr. W. J. Kacer on Deceuber 6, 1979, in a telephone conversation with Mr. J. E. Konklin of your office.

Description of the Deficiency Great Lakes Construction Company is required, by specification, to construct a double Class "B" Fill waterstop around all piping which penetrates the Class "A" Fill surrounding the main plant buildings. The Resident Geotechnical Engineer identified that the requirements were not being implemented. The contractor initiated a Nonconfornance Report, NR-GLC 526, providing a listing of all piping and waterstops installed as of December 14, 1979.

There are 28 locations where waterstops were required. At eight locations, the double waterstops have been installed; at seven locations, single waterstops varying in width from 4' to 16' have been installed; and waterstops have not been installed at the remaining locations.

The information available is presently being evaluated so that a dis-position of the nonconformance can be provided to the contractor.

A final report will be submitted to the NRC by February 29, 1979.

Very truly yours, A

k. d~ * 'L D. R. Davidson Vice President System Engineering and Construction 1747 102 cc: Victor Stello, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission f$