e ENCLOSURE SEQUOYAH NUCLEAR PLANT UNIT 2 INAPPROPRIATE SEISMIC ANALYSIS OF UHI PIPING NCR CEB 79-36 10 CFR 50.55(e)
FINAL REPORT Description of Condition The seismic analysis of record for the 12-inch UHI piping in unit 2, from the gas to the water accumulators, is the unit 1 analysis since the piping is opposite hand. However, the building which houses the unit 2 UHI piping is physically different from the unit 1 building.
This requires the use of a different seismic response spectra in the piping analysis for unit 2.
This discrapancy'was overlooked in the original seismic analysis.
Safety Implications Had this condition gone uncorrected, the safety-related UHI piping could have been adversely affected during a seismic event.
Corrective t.ction The unit 2 piping will be reanalyzed using the appropriate seismic response spectra. Any required hardware modifications will be com-pleted before unit 2 fuel loading.