Final Rept Re Potential Significant Deficiency Involving Improper Installation & Insp of Embedded Plate Assemblies. Caused by Deficiency in Const & Breakdown in QA Program. QA Program Upgraded & Embed Design ModifiedML19257A321 |
Person / Time |
---|
Site: |
Vogtle |
---|
Issue date: |
11/20/1979 |
---|
From: |
GEORGIA POWER CO. |
---|
To: |
|
---|
Shared Package |
---|
ML19257A320 |
List: |
---|
References |
---|
NUDOCS 8001030734 |
Download: ML19257A321 (4) |
|
|
---|
Category:DEFICIENCY REPORTS (PER 10CFR50.55E & PART 21)
MONTHYEARML18016A9011999-04-12012 April 1999 Part 21 Rept Re Defect in Component of DSRV-16-4,Enterprise DG Sys.Caused by Potential Problem with Connecting Rod Assemblies Built Since 1986,that Have Been Converted to Use Prestressed Fasteners.Affected Rods Should Be Inspected ML20236V3121998-07-29029 July 1998 Final Part 21 Rept Re Enterprise DSR-4 & DSRV-4 Edgs.Short Term Instability Was Found During post-installation Testing & Setup as Part of Design mod/post-work Testing Process. Different Methods Were Developed to Correct Problem ML20248A1671998-05-22022 May 1998 Interim Part 21 Re Enterprise DSR-4 & DSRV-4 Emergency diesel.Post-installation Testing Revealed,High Em/Rfi Levels Affected New Controllers,Whereas Original Controllers Were unaffected.Follow-up Will Be Provided No Later than 980731 ML17309A6211997-09-29029 September 1997 Part 21 Rept Re Final Disposition of Masterflow 713 & Embeco 636 Grout Nonconformance Reported by Master Builders,Inc. Licensee Continuing to Monitor shelf-life of Masterflow 713 & Embeco 636 Grouts Produced at Rancho Cucamonga ML20140G4481997-05-0101 May 1997 Part 21 Rept Re Potential Defect in Component of Dsrv & Dsr Enterprise Standby Diesel Generator Sys.Recommends That Springs Be Inspected on Periodic Basis,Such as During Refueling Outages ML20133E8001997-01-0808 January 1997 Deficiency Rept Re Nonconformance Related to Masterflow 713 Grout,Which Master Builders,Inc Has Supplied as Nuclear SR Product to 18 Npps.Cause Unknown.Requests That Listed Info Be Provided to Gain Insight as to Scope & Possible Cause ML20134H3361996-11-0505 November 1996 Part 21 Rept Re Defective Inner Thrust Bearing 1801461-01 Used in PSA 35 Mechanical Shock Arrestor Used as Restraint on Piping Sys for Nuclear Generating Plant.Lot of Defective Parts Located & Isolated to Three Customers ML20115D2001996-07-0909 July 1996 Part 21 Rept Re Mfg Defect of Enterprise DSR-4 & DSRV-4 Edgs,Originally Mfg by Calcon Corp.Amot Control Corp Purchased Calcon Product Line & Maintains Design & Production.Valves Returned to Cooper Energy Svcs on 960131 ML20117G4641996-05-14014 May 1996 Part 21 Rept Re Cooper Bessemer Reciprocating Products,Div of Cooper Cameron Corp,Issued Ltr to Define Utils/Plants Containing Similar Equipment as Supplied on Cooper Bessemer Ksv & Enterprise Dsr EDGs ML18038A8971994-09-0707 September 1994 Part 21 Rept Re Defect in Latching Mechanism of Potter & Brumfield Relay on C&D High Voltage Shut Down Alarm Assembly Printed Circuit Boards.Pull Test on Relay Reset Button Incorporated Into Receiving Insp Procedures ML20059H7721994-01-17017 January 1994 Part 21 Rept Re Virginia Power Notifying Fairbands Morse Via Failure Analysis Rept NESML-Q-058 of Defective Air Start Distributor cam,16104412 ML20059F2631994-01-0707 January 1994 Part 21 Rept Re Air Start Distributor Cam Mfg by Fairbanks Morse.Mfg Suggests That Site Referenced in Encl App I Inspect Air Start Distributor Cam as Soon as Practical ML20058K3841993-12-0909 December 1993 Part 21 Rept Re Potential Defect in Component of Dsrv & Dsr Enterprise Standby DG Sys,Regarding Potential Problem W/ Subcover Assembled Atop Power Head ML20127H2301993-01-15015 January 1993 Part 21 Rept Re Potential Defeat in Component of Dsrv & Dsr Enterprise Standby DG Sys.Starting Air Distributor Housing Assemblies Installed as Replacement Parts at Listed Sites ML20126J5961992-12-31031 December 1992 Part 21 Rept Re Potential Loss of RHR Cooling During Nozzle Dam Removal.Nozzle Dams May Create Trapped Air Column Behind Cold Leg Nozzle Dam.Mod to Nozzle Dams Currently Underway. Ltrs to Affected Utils Encl ML20126B0421992-12-17017 December 1992 Final Part 21 Rept Re Potential Problem W/Steel Cylinder Heads.Initially Reported on 921125.Caused by Inadequate Cast Wall Thickness at 3/4-inch-10 Bolt Hole.Stud at Location Indicated on Encl Sketch Should Be Removed ML20127D1491992-09-0404 September 1992 Part 21 Rept Re Defect in Component of DSRV-16-4 Enterprise Standby DG Sys Jacket Water Pump Shaft.Caused by Incorrect Tapers Machined on Shaft Due to Vendor Mismatching.All Affected Shafts Recalled & Quality Insp Plans Changed ML17289A6971992-06-26026 June 1992 Amend 1 to Part 21 Rept 158 Re gear-wear Induced Failures in engine-driven Jacket Water Pump in DSRV-16-4 Standby DG Sys. Initially Reported on 911029.Grand Gulf Station Observed Wear Characteristics in as Little as 500 Operating Hours ML20094L1271992-03-13013 March 1992 Amend 1 to Part 21 Rept 159 Re Potential Defect in Power Cylinder Liner.Initially Reported on 920115.Caused by Liner/ Block Fit & Localized Matl Microstructure.All Drawings & Specs Revised to Address Matl Design Requirements ML20087D3191992-01-14014 January 1992 Potential Part 21 Rept Re Problems W/Elmwood/Fasco Contactor Carriers Breaking in Contactor Model 30-FO-30. Caused by Distortion/Shrinkage of Molded Phenolic Contactor Carrier.Replacement Contactors Installed ML17223A5941990-03-0909 March 1990 Errata to 900126 Part 21 Rept Re Anchor/Darling Actuators Incorporating Use of Teldyne-Republic four-way Valves.Lists Plants Inadvertently Left Out in Original Rept ML20005G6831990-01-0505 January 1990 Part 21 Rept Re Installation Instructions for Grommet Use Range for Patel Conduit Seal P/N 841206.Conduit Seals in Environ Qualification Applications Inspected for Proper Wire Use Range & Grommets Replaced ML20248E0121989-09-13013 September 1989 Supplemental Part 21 Rept Re Potential Problem W/Six Specific Engine Control Devices in Air Start,Lube Oil, Jacket Water & Crankcase Sys.Initially Reported on 890429. California Controls Co Will Redesign Valve Seating ML20246K7401989-04-26026 April 1989 Part 21 Rept Re Incorrectly Stamped Name Plates on Certain Asco Nuclear Qualified Valves.Vendor Will Contact Each Affected Facility & Furnish Correctly Stamped Plates & in Near Future Discontinue Sale of Rebuild Kits for Valves ML20247P7991989-04-0404 April 1989 Part 21 Rept Re Atmospheric Dump Valves.Cause of Failure Speculative But Result of Piston Ring That Failed to Seal. Resolution to Problem Requires Increasing Pilot Valve Capacity & Reworking of Plug to Enlarge Pilot Flow Area ML20206M4401988-11-21021 November 1988 Deficiency Rept Re Misapplication of Raychem Criteria in Selection of Some Matl Used in Electrical Cable Field Splice Kits.Initially Reported on 880920.Investigation Is in Process.Final Rept Will Be Submitted by 881222 ML20205C9291988-10-18018 October 1988 Part 21 & Deficiency Rept Re Valves Installed Opposite to Direction of Flow,Per 10CFR21 & 50.55 Requirements.Item Being Tracked by MTS EAI B-5115 & Scheduled for Completion 881030 ML20205D6651988-10-18018 October 1988 Part 21 & Deficiency Rept Re Penetration Seals Found Not to Be Watertight.Initially Reported on 880609.Water Leakage Tests Performed on Unit Upper Cable Spreading Room Seals. All Floor Penetration Seal Assemblies Repaired ML20207P0451988-10-0505 October 1988 Part 21 Rept 146 Re Defect in Left Intercooler Inlet Adapter on Standby Diesel Engine Generator.Recommends Utils Inspect Left Intake Manifold Drain as Part of Operating Plan.Addl Info Expected by 881015 ML20155D6471988-09-28028 September 1988 Deficiency Rept Re Valves Installed Opposite to Direction of Flow.Initially Reported on 880629.Final Rept Delayed Until 881020 ML20207J7361988-09-20020 September 1988 Interim Deficiency Rept Re Misapplication of Vendor Criteria in Selection of Some Matl Used in Electrical Cable Field Splice Kits.Initially Reported on 880601.Final Rept Expected Prior to 881123 ML20153E2271988-09-0101 September 1988 Part 21 & Deficiency Rept Re ESF Filtration Unit Bolts. Initially Reported on 880628.Contractor Conducted Training Session for Personnel to Stress Importance of Clarifying Incomplete Drawing Info & Requirements of Bolting Procedure ML20151V1901988-08-16016 August 1988 Deficiency Rept Re non-water Tight Penetration Seals.Test Rig Constructed to Simulate Typical Upper Cable Spreading Room Configuration & Sealants Verified to Provide Waterproof Seal.Next Rept Will Be Submitted by 881020 ML20196L4811988-07-0707 July 1988 Part 21 & Deficiency Rept Re Valves Installed Opposite to Direction of Flow.Initially Reported on 880601.Investigation in Progress to Determine Full Scope of Condition.Final Rept Will Be Submitted by 881001 ML20151A7781988-07-0606 July 1988 Deficiency Rept Re nonwater-tight Penetration Seals. Initially Reported on 880609.Investigation Incomplete.Next Rept Expected by 880818 ML20196C2971988-06-28028 June 1988 Deficiency Rept Re ESF Filtration Bolts.Initially Reported on 880601.Investigation of Root Cause of Condition Ongoing. Final Rept Will Be Submitted by 880901 ML20195D8541988-06-16016 June 1988 Part 21 Rept Re Potentially Reportable Condition Associated W/Dresser Model 7440W Check Valves Supplied W/Flow Direction Arrow Stamped Opposite to Valve Flow.Investigation Being Conducted.Evaluation of Bechtel Western Power Co Ltr Encl ML20154J4101988-05-12012 May 1988 Addendum 1 to Supplemental Part 21 Rept 145 Re Potential Problem w/F-573-156 Pressure Sensor/Lube Oil Trip.Initially Reported on 880429.Addl 1-1/8-inch Diameter W/Deep Counterbone in Pressure Head Added to Activate Valve ML20154A6841988-05-10010 May 1988 Deficiency Rept Re Electrical Cable Tray Separation. Initially Reported on 880414.Walkdown of All safety-related Cable Trays Conducted to Ensure Any Unacceptable Separation Distance Identified ML20153B6191988-04-29029 April 1988 Part 21 Rept Re Potential Defect in Component of Dsr or Dsrv Standby Diesel Generators Supplied to Utils.Recommends Return of Subj Components in Onsite Warehouse Storage & Suggests Surveillance of Devices Already Installed ML20151K2621988-04-14014 April 1988 Interim Deficiency & Part 21 Rept Re Control Room Essential HVAC Sys.Initially Reported on 870914.Addl Concern Noted Re Incorrect Assumption in Design Calculation.Corrective Action Beyond Calculation Review Involves Logic Mod ML20151K2371988-04-14014 April 1988 Part 21 & Deficiency Rept Re Damage to Emergency Diesel Generator Jacket Water HX During Flushing.Initially Reported on 860917.HX Repaired & Installed in Unit 2.Thermostatic Valves Being Modified ML20148R6441988-01-27027 January 1988 Part 21 & Deficiency Rept Re Protection of Containment Electrical Penetration Assemblies Fabricated by Conax Buffalo Corp.Initially Reported on 871203.LOCA Could Cause One or More of nonsafety-related Circuits to Short Circuit ML20237E9941987-12-22022 December 1987 Deficiency Rept Re Protection of Containment Electrical Penetration Assemblies (Epa).Initially Reported on 871203. Investigations in Progress.Final Rept Will Be Submitted by 880130 ML20236V2981987-11-19019 November 1987 Deficiency Rept Re Electrical Separation Criteria Specified in Const Spec X3AR01.Initially Reported on 870909.Second Test of Electrical Separation Requirements Very Positive. Final Rept Expected to Be Submitted Prior to 880301 ML20236K1431987-11-0202 November 1987 Interim Part 21 & Deficiency Rept Re Inductive Current Interruptive Capacity of Solid State Protection Sys Motor Driven Relay Contacts.Shunt Suppression Device Will Be Added to Solenoid ML20236J5371987-10-29029 October 1987 Part 21 & Deficiency Rept Re Solid State Protection Sys motor-driven Relay Contacts Inductive Current Interruptive Capacity.Initially Reported on 870110.Hardware Mods to Affected Circuits Planned Prior to Fuel Load ML20239A2111987-09-14014 September 1987 Part 21 & Deficiency Rept Re Design of Control Room Essential (CRE) HVAC Sys.Initially Reported on 870713. Backdraft Dampers Added to Unit 1 CRE HVAC Units & Will Be Added to Unit 2 Commensurate W/Const Schedule ML20237H7741987-08-12012 August 1987 Interim Deficiency Rept Re Emergency HVAC Sys in Control Room.Initially Reported on 870713.Engineering Evaluation in Progress to Determine Potential Impacts of Condition on Plant Safety.Final Rept Will Be Submitted by 870915 ML20216E4721987-05-28028 May 1987 Part 21 Rept 140 Re Potential Defect in Air Pressure Regulators Mfg by Bellofram.Dripwell Gasket May Fail Due to Mismachining of Gasket Seating Surface Causing Loss of Control Air & Starting Air Pressure 1999-04-12
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217K4591999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Vogtle Electric Generating Plant,Units 1 & 2.With ML20217K8041999-09-30030 September 1999 Rev 1 to Vegp,Unit 2 Cycle 7 Colr ML20217K7741999-09-30030 September 1999 Rev 1 to Vegp,Unit 1 Cycle 9 Colr ML20216E5061999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Vegp,Units 1 & 2. with ML20210P9841999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Vogtle Electric Generating Plant,Units 1 & 2.With ML20209H1211999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Vogtle Electric Generating Plant,Units 1 & 2.With ML20196F9711999-05-31031 May 1999 Owner Rept for ISI for Vogtle Electric Generating Plant, Unit 1 Eighth Maint/Refueling Outage ML20195G1731999-05-31031 May 1999 Monthly Operating Repts for May 1999 for VEGP Units 1 & 2. with ML20206N2141999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Vogtle Electric Generating Plant,Units 1 & 2.With ML20206A6561999-04-21021 April 1999 Safety Evaluation Authorizing Licensee Re Rev 9 to First 10-year ISI Interval Program Plan & Associated Requests for Relief (RR) 65 from ASME Boiler & Pressure Vessel Code ML18016A9011999-04-12012 April 1999 Part 21 Rept Re Defect in Component of DSRV-16-4,Enterprise DG Sys.Caused by Potential Problem with Connecting Rod Assemblies Built Since 1986,that Have Been Converted to Use Prestressed Fasteners.Affected Rods Should Be Inspected ML20206C2291999-03-31031 March 1999 Revised Monthly Operating Repts for Mar 1999 for Vogtle Electric Generating Plant,Units 1 & 2 ML20205Q8081999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Vegp,Units 1 & 2. with ML20205A9581999-03-31031 March 1999 Rev 0 to VEGP Unit 1 Cycle 9 Colr ML20207K6051999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Vogtle Electric Generating Plant,Units 1 & 2.With ML20209H3951999-02-15015 February 1999 Rev 2 to ISI Program Second 10-Year Interval Vogtle Electric Generating Plant Units 1 & 2 ML20209H4091999-02-15015 February 1999 Rev 1 to ISI Program Second 10-Year Interval Vogtle Electric Generating Plant Units 1 & 2 ML20202H9851999-01-29029 January 1999 Safety Evaluation Accepting Rev 8 to First 10-year Interval Inservice Insp Program & Associated Requests for Relief for Vogtle Electric Generating Plant,Unit 1 ML20199F8041999-01-13013 January 1999 Corrected Pages to VEGP-2 ISI Summary Rept for Spring 1998 Maint/Refueling Outage ML20199E7561998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Vogtle Electric Generating Plant,Units 1 & 2.With ML20198S1781998-12-31031 December 1998 SER Re Second 10-year Interval Inservice Insp Program Plan & Associated Requests for Relief for Southern Nuclear Operating Co,Inc Units 1 & 2 ML20196E5221998-12-0101 December 1998 Rev 8 to ISI-P-014, ISI Program for VEGP-2 ML20198B8571998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Vogtle Electric Generating Plant,Units 1 & 2.With ML20195H2131998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Vogtle Electric Generating Station,Units 1 & 2.With ML20154L5681998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Vegp,Units 1 & 2 ML20151W3681998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Vogtle Electric Generating Plant Units 1 & 2.With ML20154L5721998-08-31031 August 1998 Corrected Page from MOR for Aug 1998 for Vegp,Unit 2 ML20237D2051998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Vogtle Electric Generating Plant Units 1 & 2 ML20236V3121998-07-29029 July 1998 Final Part 21 Rept Re Enterprise DSR-4 & DSRV-4 Edgs.Short Term Instability Was Found During post-installation Testing & Setup as Part of Design mod/post-work Testing Process. Different Methods Were Developed to Correct Problem ML20236P6991998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Vogtle Electric Generating Plant,Units 1 & 2 ML20236Q3051998-06-30030 June 1998 Owner'S Rept for ISI for Sixth Maint/Refueling Outage of Vogtle Electric Generating Plant,Unit 2 ML20249A3911998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Vogtle Electric Generating Plant ML20248A1671998-05-22022 May 1998 Interim Part 21 Re Enterprise DSR-4 & DSRV-4 Emergency diesel.Post-installation Testing Revealed,High Em/Rfi Levels Affected New Controllers,Whereas Original Controllers Were unaffected.Follow-up Will Be Provided No Later than 980731 ML20249A3931998-04-30030 April 1998 Revised MOR for Apr 1998 for Vogtle Electric Generating Plant Unit 1 ML20247F3841998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Vogtle Electric Generating Plant,Units 1 & 2 ML20154Q9721998-04-20020 April 1998 10CFR50.59(B) Rept of Facility Changes,Tests & Experiments for Vogtle Electric Generating Plant,Units 1 & 2 ML20217H7181998-04-0101 April 1998 Corrected Page 5 to 980324 SER Re Relief Requests Associated W/Second 10-year Interval Insp program.RR-21 in Error in That Component,Suction Damper Inadvertently Omitted. Corrected Page 7 of Technical Ltr Rept Also Encl ML20216D6141998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Vogtle Electric Generating Plant,Units 1 & 2 ML20217Q1301998-03-31031 March 1998 Rev 0 to Vepc Unit 2 Cycle 7,COLR ML20217B8831998-03-24024 March 1998 SER Accepting Relief Request RR-5,RR-19,RR-20,RR-21,RR-23 & RR-24 for Second 10-yr Interval ISI Program Plan ML20216E2421998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Vogtle Electric Generating Plant,Units 1 & 2 ML20203H9551998-02-23023 February 1998 SER Denying Quality Assurance Program Description Change for Vogtle Electric Generating Plant,Units 1 & 2 ML20203E4831998-02-11011 February 1998 Rev 1 to Vogtle Electric Generating Plant,Units 1 & 2 Second Ten-Yr Interval Pump Inservice Test Program ML20198T1211998-01-31031 January 1998 Owners Rept for Inservice Inspection for Seventh Maintenance/Refueling Outage ML20202G5441998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Vogtle Electric Generating Plant,Units 1 & 2 ML20199E5431998-01-31031 January 1998 Rev 3 to WCAP-14720, Vogtle Units 1 & 2 Spent Fuel Rack Criticality Analysis W/Credit for Soluble Boron ML20198L6471997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Vogtle Electric Generating Plant,Units 1 & 2 ML20203C2811997-12-0909 December 1997 Safety Evaluation Authorizing Request for Relief of Second 10 Yr Interval Inservice Insp Program ML20202B7881997-12-0101 December 1997 Rev 8 to ISI-P-006, ISI Program for Gpc Vogtle Electric Generating Plant Unit 1 ML20203H0601997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Vegp,Units 1 & 2 1999-09-30
[Table view] |
Text
'
Page 1 of 4 GEORGIA POWER C0f1PANY ALVIN W. V0GTLE NUCLEAR PLANT - UNITS 1 & 2 DOCKET: 50-424 and 50-425 EMBED PLATE ASSEf1BLIES FINAL REPORT November 20, 1979 INITIAL REPORT TO NRC: Verbal report by telephone on November 21, 1978, to Bob Wright (NRC, Region II) by Mr. C. W. Hayes (GPC QA Department)
INTERIM REPORTS TO NRC: 1) Letter W. E. Ehrensperger to J.P. O'Reilly datac December 20, 1978
- 2) Letter W. E. Ehrensperger to J. P. O'Reilly dated February 22, 1979
- 3) Letter W. E. Ehrensperger to J. P. O'Reilly dated June 1, 1979
- 4) Letter Doug Dutton to J. P. O'Reilly dated July 31, 1979
- 5) Letter Doug Dutton to J. P. O' Reil'y dated October 8, 1979 Descriotion of Occurrence The following description was previously reported in the above referenced Interim Reports. A potential significant deficiency was observed at Plant Vogtle on November 21, 1978 involving the improper installation and inspection of embedded plate assenblies.
An embedded plate assembly consists of a steel plate of specified dimen-sions with hexagonal nuts (" plate nuts") welded to the embedded side, an inspec-tion hole drilled through the plate concentric with the " plate nut", a bolt treaded into and tack welded to the plate nut, and a washer and another nut ("end nut") threaded on to and tack welded to the opposite end of each bolt.
The following deficiencies were noted and previously reported in the interim reports of certain embed assemblies in the auxiliary and control buildings:
- 1) Some of the bolts for a given embed plate were not fully engaged with the plate nut.
- 2) Some of the bolts in a given assembly did not have washers.
1668 318 8001080 "7 g3'-l
' Page 2 of 4
- 3) Some of the bolts did have washers, but the washers were not tack welded to the bolt.
- 4) Some of the end nuts were not tack welded to the bolt. (Note:
design drawings show a tack weld between bolt and end nut).
- 5) Some of the bolts were n t tack welded to the plate nut.
- 6) Some of the bolts may have beenU bent in excess of the design drawings' specified angle of 30 .
- 7) Some of the bolts could have developed cracks due to excess bending.
- 8) The plate nut and end nut in each poured embed assembly are standard hexagonal nuts instead of heavy hexagonal nuts as identified on the design drawing.
- 9) The possibility of cracks in the fillet weld around plate nuts due to pressure applied to bend anchor bolts.
- 10) Some of the bolts were missing completely on assemblies not yet covered in concrete. (This deficiency was not previously reported in the interim reports).
Analysis of Safety Imolications This deficiency represents a deficiency found in construction which, were it to have remained uncorrected, possibly could have adversely affected the safety of operations of the nuclear power plant. The deficiency also reflected a significant breakdown in a portion of the Quality Assurance Program according to the requirements of 10CFR50, Appendix B.
The deficiency possibly could have resulted in inadequate support of piping, HVAC, or other systems in the auxiliary or control buildings, with poten-tial consequences on the safety of operation of the nuclear power plant through-out the expected lifetime of the plant.
The deficiency caused extensive evaluation, testing, and some repair to embed plates to establish their adequacy to perform their intended safety function.
The load carrying capacity of some embed plates was derated by Engineering and a few plates were abandoned entirely.
Corrective Action A detailed investigation was conducted on site to determine the "as built" condition of fabri::ated and installed embed plate assemblies. The results of this investigation was transmitted to Engineering and Licensing. Engineering per-formed an analysis of the embed assemblies data and recommended the necessary action to bring the embed assemblies in compliance with the design criteria, Based on Engineering's analysis and recommendation, the following action was taken by GPC:
1668 319
Page 3 of '4 4
- 1) Bolts with thread engagement between 40% and 80% were plug welded using the Engineering approved plug welding procedure.
- 2) Bolts with less than 40% thread engagement were abandoned.
- 3) Ultrasonic inspection on each embed plate assembly was conducted to determine:
a) whether or not the bolt was stra'ight; b) whether or not ghe bolt was bent greater than 20 , bolts bent greater than 20 was considered cracked and were abandoned; c) whether or not a bolt had been reincated using the relocation parameter of within 3" from locatiorr on plate as allowed on engineering drawinn; and d) whether or not there were cracks or voids in the fillet weld.
- 4) To determine the presence of the "end nut" and to verify compliance with design requirements, the following actions were taken:
a) Engineering developed procedures for pull testing of the embed plate assemblies. To assist in qualifying the procedure and gaining experience with the test equipment, Georgia Power Company poured a test block with embed plates containing the various postulated deficiencies including some plates with out any end nuts. These plates were pulled tested and the test data was sub-mitted to Engineering.
b) Engineering modified their procedure prior to testing actual installed embed assemblies to assure that sufficient load was applied to break the bond between the concrete and the bolt, therefore, assuring the presence of the end nuts. A random sample was taken and approximately seventy-five bolts were tested with no failures.
c) Probability analysis and test statistics indicate a high confi-dence le/el regarding the perforrance of the embedded plates for the service intended.
d) All embed plates with only four bolts could not be demonstrated as meeting the design requirenents based on the statistical probability used. All embed plates with only four bolts were pull tested to determine their adequacy.
- 5) A few embed plates were abandoned.
Based on the Engineering analysis no additional action was required for:
- 1) Bolts determined to have 80% or greater thread engagement in a standard nut.
- 2) Use of the standard hex nut instead of the heavy hext nut.
- 3) Omission of a washer.
1668 320
Page 4 of 4
- 4) Lack of tack welding of the bolt to the plate nut since the presence of the bolt could be verified through the inspection hole.
As reported in our interim letter of February 22, 1979, the continuous upgrading of our QA Program along with our continuing training program has signi-ficantly improved our field's QC surveillance. Additionally, the embed design has been modified, where practicable, to specify Nelson studs in lieu of the bolt and nut assembly. It is our opinion that adequate corre tive action has been taken.
Summary and Conclusions
- 1) This deficiency, were it to.have remained uncorrected, could possibly have affected adversely the safety of operations of the nuclear power plant at some time during the expected lifetime of the plant.
- 2) The deficiency represents a significant breakdown in a portion of the QA Program as outlined in 10CFR50, Appendix B.
- 3) The deficiency does not represent a significant deficiency in final design. -
- 4) The deficiency represents a significant deficiency in construction of a component.
- 5) Based on items 1, 2 & A, the Georgia Power Company concludes that the deficiency comes under the reportino requirements of 10CFR50.55(e).
Records of the foregoing activities are located at the Plant Vogtle con-struction site and are available for your review. Based on the results of our evaluation, Georgia Power Company's embed plates are in conoliance with design requirements and no additional testing is planneci for installed plates.
1668 321