Responds to IE Bulletin 79-18 Re Audibility Problem Encountered on Evacuation of Personnel.Engineering Survey Conducted to Determine Areas of Plant Where Evacuation Announcement & Alarm Sys Inaudible or Invisible
ML19257A243
Person / Time
Site: Yankee Rowe
Issue date: 11/28/1979
From: Moody D
YANKEE ATOMIC ELECTRIC CO.
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
IEB-79-18, NUDOCS 8001030213
Download: ML19257A243 (2)


Text

$

Y%

e Telephone 617 366-90ll rwx 7I0-390-0739 YANKEE ATOMIC ELECTRIC COMPANY e.a.2.1 WYR 79 148

( Yaux,es 20 Turnpoke Road Westborough, Massachusetts 01581 gl N.~~

November 28, 1979 United States Nuclear Regulatory Commission Office of Inspection and Enforcement Region I 631 Park Avenue King of Prussia, Pennsylvania 19406 Attention:

Mr. Boyce H. Grier, Director

Reference:

(a) License No. DPR-3 (Docket No. 50-29)

(b) Letter USNRC to YAEC dated August 7, 1979, I&E Bulletin No. 79-18

Dear Sir:

Subject:

Response to I&E Bulletin No. 79-18 The following information is being furnished in response to Reference 03).

The item numbers used are identical to the numbers in your request.

1.

The plant has conducted an Engineering Survey to determine those areas of the plant where the evacuation announcement and alarm systems were not audible or visible. The areas were surveyed at maximum anticipated noise levels. The results of this survey indicated that there were some deficiencies in the plant's communications system in various high noise areas in the plant.

2.

The corrective actions being taken by the plant include:

a)

Upgrading the in-plant communications in high noise areas to assure audibility at maximum background noise levels.

b)

Installation of new speakers in areas where there previously were no installations.

c)

Installation of an evacuation tone signal that will broadcast an evacuation alarm through the plant cornunication system.

8001030 1[3

4 4

United States Nuclear Regulatory Commission Attention:

Mr. Boyce H. Grier November 28, 1979 Page 2 d)

In vary high noise areas such as the diesel generator cubicles, flashing warning lights have been installed to alert personnel in the event of a plant emergency.

These warning lights will be actuated by an audible frequency to voltage transducer.

3.

This report is submitted in compliance with Item 3.

4.

All the corrective actions outlined in Item 2 were scheduled to be completed by December 5, 1979, however, equipment procurement lead time may delay completion beyond the December 5, 1979 target date.

The equipment necessary to complete the actions taken is expected to be on site by January 15, 1980.

We trust this survey adequately addresses the concerns of the I&E Bulletin.

If you require further information with regards to this bulletin, please contact us.

Very truly yours, YANKEE ATOMIC ELECTRIC COMPANY h.

D E. Moody