Forwards IE Insp Rept 50-348/79-33 on 791010-12 & 19.No Noncompliance Noted
ML19256G435
Person / Time
Site: Farley 
Issue date: 11/15/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Clayton F
ALABAMA POWER CO.
Shared Package
ML19256G436 List:
References
NUDOCS 7912310292
Download: ML19256G435 (2)


See also: IR 05000348/1979033

Text

f/c

M M00

!( 3

'o,,

UNITED STATES

M.-8Y5'

,

NUCLEAR REGULATORY COMMISSION

o

5

'.

.: E

REGION 11

,

'#

"

o

101 MARIETTA ST.. N.W.. SUITE 3100

%./

ATLANTA. o EoRGIA 30303

NOV 15 b/9

In Reply Refer To:

RII:WPA

50-348/79-33

Alabama Power Company

Attn:

F. L. Clayton, Jr.

Senior Vice President

Post Office Box 2641

Birmingham, Alabama 35291

Gentlemen:

This refers to the inspection conducted by W. P. Ang of this office on October 10-

12, 1979 and October 19, 1979 of activities authorized by NRC License No. NPF-2

for the Farley Nuclear Plant facility, and to the discussion of our findings

held with W. G. Hairston at the conclusion of the inspection at Farley Nuclear

Plant and with R. George at the conclusion of the inspection at EDS Nuclear.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were disclosed.

We have examined actions you have taken with regard to previously reported

unresolved items. The status of these items is discussed in the enclosed report.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe to be

proprietary, it is necessary that you make a written application within 20 days

to this office to withhold such information from public disclosure. Any such

application must include a full statement of the reasons on the basis of which

it is claimed that the information is proprietary, and should be prepared so

that proprietary information identified in the application is contained in a

separate part of the document.

If we do not hear from you in this regard within

the specified period, the report will be placed in the Public Document Room.

1664

196

, ;,nw u 959- Q

.

.

NOV 151979

Alabama Power Company

-2-

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

< . " '

,

,

C. E. Murphy,

R

Reactor Construction and

Engineering Support Branch

Enclosure:

Inspection Report No. 50-348/79-33

cc w/ enclosure:

A. R. Barton

E: ecutive Vice President

Post Office Box 2641

Birmingham, Alabama 35291

J. T. Young

Vice President-Production

Post Office Box 2641

Birmingham, Alabama 35291

H. O. Thrash

Manager-Nuclear Generation

Post Office Box 2641

Birmingham, Alabama 35291

4

g7

C. Biddinger, Jr.

Manager-Corporate Qua'ity Assurance

Post Office Box 2641

Birmingham, Alabama 35291

W. G. Hairston, III

Plant Manager

Drawer 470

Ashford, Alabama 36312

R. E. Hollands, Jr.

QA Supervisor

Post Office Box U

Ashford, Alabama 36312