Confirms Commitments in Response to short-term Recommendations of TMI-2 Lessons Learned Task Force on Mod of Automatic Valve Reopening Circuit.Mod to Be Completed by 800101 or Prior to Critical Operation
ML19256G147
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 12/20/1979
From: Kelly R
GEORGIA POWER CO.
To:
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0578, RTR-NUREG-578 NUDOCS 7912270519
Download: ML19256G147 (1)


Text

Georgia Power Cornpany 230 Peachtree Street Post Office Box 4545 Atlanta Georgia 30302 Telephone 404 522-6060 December 20, 1979 L

Georg. Power R. J. Kelly ia Vice President and General Manager Pcwer Generaton

ne sourrem eec:nc sjstem Director of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Warhington, D. C.

20555 NRC DOCKET 50-321 OPERATING LICENSE DPR-57 EDWIN I. HATCH NUCLEAR PLANT UNIT 1 CONFIRMATION OF COMMITMENTS REGARDING THE SHORT-TERM RECOMMENDATIONS OF TMI-2 LESSONS LEARNED TASK FORCE Gentlemen:

Pursuant to the request of members of the Nuclear Regulatory Commission's staff, Georgia Power Company wishes to take this opportunity to confirm our intentions of meeting those Unit 1 schedule commitments contained in our letters of October 19 and November 21, 1979.

The response to item 2.1.4, Containment Isolation Provisions for BWR's, is hereby revised to cocmit to a modification of the automatic valve reopening circuit which will achieve the desired result of preventing the reset action from opening the isolation valves. This is accomplished by requiring each valve operating switch to be placed in the " closed" position before reset can be achieved. Each of the valves can then be opened individually as required following trip logic reset. This mcdification wi.11 be completed by January 1, 1980, or prior to Unit 1 critical operation, whichever is later, and will fulfill Georgia Power Company's commitment to provide a solution to the requirements of this item.

It should be noted that in the case of Item 2.1.2 of NUREG-0578, Relief and Safety Valve Testing, the BWR Owners Group's position is currently being revised with final resolution to come in 1980. Georgia Power Company endorses the position described in correspondence between Mr. T. D. Keenan, Chairman of the BWR Owners Group, and Mr. D. E. Eisenhut, Acting Director of the Divison of Operating Reactors, in this matter.

If further clarification is required, please contact this office at your earliest convenience.

Very truly yours, MM Oyo R. J. ge117 s

1645 019 Mo WEB /mb xc: Ruble A. Thomas George F. Trowbridge, Esquire Q

IQ1gp)g

/

1. F. Rogers, III