Forwards IE Bulletin 79-28, Possible Malfunction of Namco Model EA180 Limit Switches at Elevated Temps. Action Required
ML19256F680
Person / Time
Site: Hatch, Vogtle  Southern Nuclear icon.png
Issue date: 12/07/1979
From: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
References
NUDOCS 7912200038
Download: ML19256F680 (2)


Text

f

/C

/

'o UNITED STATES 8%

NUCLEAR REGULATORY COMMISSION 3,

n

^

E REGION 11

{ ^ ai -

g'f s

o 101 MARIETTA ST., N.W.. SUITE 3100 g

U ATLANTA, GEORGIA 30303 DEC 7 1m.,,

In Reply Refer To:

DJPO

~~s 321, J W 50-424, 50-425 Georgia Power Company Attn:

J. H. Miller, Jr.

Executive Vice President 270 Peachtree Street, N.W.

Atlanta, Georgia 30303 Gentlemen:

Enclosed is IE Bulletin No. 79-28 which requires action by you with regard to your power reactor facility (ies) with an operating license or a construction permit.

Should you have questions regarding this Bulletin or the actions required of you, please contact this office.

Sincerely,

. -m -

y,

,m y James P. O'Reilly Director

Enclosures:

1.

IE Bulletin No. 79-28 w/its Attachment 2.

Lis: of Recently Issued IE Bulletins

'I O24 1

7 D122 00 0 3 8

DEC 71979 a

Georgia Power Company cc w/ enc 1:

M. Manry, Plant Manager Post Office Box 442 Baxley, Georgia 31513 C. E. Belflower Site QA Supervisor Post Office Box 442 Baxley, Georgia 31513 K. M. Gillespie Construction Project Manager Post Office Box 282 Waynesboro, Georgia 30830 E. D. Groover QA Site Supervisor Post Office Box 282 Waynesboro, Georgia 30830 W. A. Widner, General Manager Nuclear Generation Georgia Power Company Post Office Box 4545 A'tlanta, Georgia 30303

~

~

f UNITED STATES SSINS Uo.: 6820 NUCLEAR REGULATORY COMMISSION Accession No..

OFFICE OF INSPECTION AND ENFORCEMENT 7910250505 WASHINGTON, D.C.

20555 December 7, 1979 IE Bulletin No. 79-28 POSSIBLE MALFUNCTION OF NAMCO MODEL EA180 LIMIT SWITCHES AT ELEVATED TEMPERATURES Description of Circumstances:

The NRC has been recently advised through a 10 CFR 21 report from Namco Controls that a malfunction of a Namco Model EA180 stem mounted limit switch (SMLS) occurred at the Cooper Nuclear Station.

Investigation into the switch failure by the licensee revealed yellow and brown " crystal-like" resin deposits on the internal components of the switch. The affected switch is located inside the drywell containment at this facility and was being used as the replacement switch for an unqualified SMLS previously identified in IE Bulletin Nos.

78-04 and 79-01.

According to the manufacturer, the problem was traced to a batch of top cover gaskets of which some were over-impregnated and insufficiently heat cured.

It has been determined that this condition can leave an uncured residue of " Loctite" in the gasket, which vaporizes at sustained temperatures above 175 F.

To correct the problem, the manufacturer has revised production techniques beginning September 1979 in order to better control the impregnation process and to properly heat cure the gaskets following impregnation.

This problem is unique to all Namco Model EA180 series switches received by licensees after March 1, 1979. According to the manufacturer, the suspect switches can be identified by checking the date code which is a 4 digit number stamped on the conduit boss of the switch housing.

Namco recommends that any EA180 series switch with a date code between 02-79 through 08-79 should have its top cover gasket replaced. Also, licensees should request from their suppliers of equipment on which Namco EA180 series switches are used that they check their inventory and replace top cover gaskets on switches date coded between 02-79 through 08-79.

The enclosed letter from Namco further describes the high-temperature environ-mental problem with the top cover gaskets used in their EA180 switches and provides recommendations to correct the problem. According to Namco, this letter has been sent to each customer who was shipped EA180 switches between February 21, 1979, and August 24, 1979.

Action to be Taken by Licensees of Powe Holders of Construction Permits:

DUPLICATE DOCUMENT 1.

Determine if your facility has ins switches in any safety-related equ Entire document previously containment, including valve posit entered into system under:

containment isolation valves.

t jg jgd No. of Pages: