ML19256F077
| ML19256F077 | |
| Person / Time | |
|---|---|
| Site: | Millstone |
| Issue date: | 10/01/1979 |
| From: | Brunner E NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Counsil W NORTHEAST NUCLEAR ENERGY CO. |
| Shared Package | |
| ML19256F078 | List: |
| References | |
| NUDOCS 7911210305 | |
| Download: ML19256F077 (2) | |
See also: IR 05000245/1979018
Text
YN
7
9
UNITED STATES
p ago
jo
NUCLEAR REGULATORY COMMisslON
y
{o
REGION I
$
f,$
431 PARK AVENUE
,
f
KING OT PRUS$1A. PENNSYLVANIA 19408
\\,
/
.....
Docket Nos. 50-245
OCT 0 1 1979
50-336
Northeast Nuclear Energy Company
ATTN:
Mr. W. G. Counsil
Vice President - Nuclear
Engineering and Operations
P. O. Box 270
Hartford, Connecticut 06101
Gentlemen:
Subject:
Combined Inspection 50-245/79-18 and 50-336/79-19
This refers to the inspection conducted by Mr. J. Shedlosky of this office on
July 1 through August 3,1979 at the Millstone Nuclear Power Station, Waterford,
Connecticut, of activities authorized by NRC License Nos. DPR-21 and DPR-65 and
to the discussions of our findings held by Mr. Shedlosky with Mr. Opeka and
other members of your staff at the conclusion of the inspection.
Areas examined during this inspection are described in the Office of Inspection
and Enforcement Inspection Report which is enclosed with this letter.
Within
these areas, the inspection consisted of selective examinations of procedures
and representative records, interviews with personnel, measurements made by the
inspector, and observations by the inspector.
Within the scope of this inspection, no items of noncompliance were observed.
In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2, Title
10, Code of Federal Regulations, a copy of this letter and the enclosed inspection
report will be placed in the NRC's Public Document Room.
If this report contains
any information that you (or your contractor) believe to be proprietary, it is
necessary that you make a written application within 20 days to this office to
withhold such information from public disclosure.
Any such application must be
accompanied by an affidavit executed by the owner of the information, which
identifies the document or part sought to be withheld, and which contains a
statement of reasons which addresses with specificity the items which will be
considered by the Commission as listed in subparagraph (.b)(4) of Section 2.790.
The information sought to be withheld shall be incorporated as far as possible
into a separate part of the affidavit.
If we do not hear from ycu in this
regard within the specified period, the report will be placed in the Public
Document Room.
1380
103
79nsto3Of
.
.
01 mg
Northeast Nuclear Energy Company
2
No reply to this letter is required; however, if you should have any questions
concerning this inspection, we will be pleased to discuss them with you.
Sincerely,
- _
'n
El
n ' . Brunner, Chief
Re ctor Operations and Nuclear
S pport Branch
Enclosure:
Office of Inspection and Enforcement Combined
Inspection Report Number 50-245/79-18 and 50-336/79-19
cc w/ encl:
J. F. Opeka, Station Superintendent
D. G. Diedrick, Manage- of Quality Assurance
J. R. Himmelwright, Licensing Safeguards Engineer