ML19256F050
| ML19256F050 | |
| Person / Time | |
|---|---|
| Site: | Davis Besse |
| Issue date: | 10/25/1979 |
| From: | James Keppler NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | Crouse R TOLEDO EDISON CO. |
| References | |
| NUDOCS 7911210040 | |
| Download: ML19256F050 (1) | |
Text
pa arog b
+f o,
UNITED STATES
! ) ) ',, (f(,g NUCLEAR REGULATORY COMMISSION
% "/f c REGION 111 gk f
799 ROOSEVELT ROAD
%.'.b" [e
o,,
GLEN ELLYN, ILLINOIS 60137 Docket No. 50-346 bN Toledo Edison Company ATTN:
Mr. Richard P. Crouse Vice President - Energy Supply Edison Plaza 300 Madison Avenue Toledo, OH 43652 Gentlemen:
This refers to my immediate action letter to you dated October 17, 1979, and to the equipment problems listed therein.
The NRC onsite inspectors have reviewed your determination of the causes of failure and the corrective actions you have taken to prevent recurrence.
The onsite team members have also inspected the equipment; observed the failed components; and observed repairs, modification, and testing of the components and equipment.
The details of our inspection findings will be contained in the inspection report to be issued as a result of this review.
We have no further questions at this time concerning these items.
Sincerely, h.- % h A _
hmes d[ Kep[lEr Director cc:
Mr. T. D. Murray, Station Superiatendent Central Files Reproduction Unit NRC 20b PDR Local PDR NSIC TIC Harold W. Kohn, Power Siting Commission Helen W. Evans, State of Ohio 1375