Forwards IE Insp Repts 50-245/79-17 & 50-336/79-18 on 790602-30.No Noncompliance Noted
ML19256E361
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 09/20/1979
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Counsil W
NORTHEAST NUCLEAR ENERGY CO.
Shared Package
ML19256E362 List:
References
NUDOCS 7911020225
Download: ML19256E361 (2)


See also: IR 05000245/1979017

Text

%

  • ..

..

p maa

UNITED STATES

{jo

NUCLEAR REGULATORY COMMisslON

[

o

REGION I

$

[ $

831 PARK AVENUE

2

KING OF PRUS$1 A, PEP:NSYl.VANI A 19406

%,.....f

Docket Nos. 50-245

3970

50-336

Northeast Nuclear Energy Company

ATTN: Mr. W. G. Counsil

Vice President - Nuclear

Engineering and Operations

P. O. Box 270

Hartford, Connecticut 06101

Gentlemen:

Subject:

Combined Inspection 50-245/79-17 and 50-336/79-18

This refers to the inspection conducted by Mr. T. Shedlosky of this office on

June 2-30, 1979 at the Millstone Nuclear Power Station, Waterford, Connecticut

of activities authorized by NRC License Nos. DPR-21 and DPR-65 and to the

discussions of our findings held by Mr. Shedlosky with Mr. Opeka and other

members of your staff at the conclusion of the inspection.

Areas examined during this inspection are described in the Office of Inspection

-

and Enforcement Inspection Report which is enclosed with this lette. .

Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, measurements made by the

inspector, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document Room.

If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure.

Any such application must be

accompanied by an affidavit executed by the owner of the information, which

identifies the dccument or part sought to be withheld, and which contains a

statement of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b)(4) of Section 2.790.

The information sought to be withheld shall be incorporated as far as possible

into a separate part, of the affidavit.

If we do not hear from you in this

regard within the specified period, the report will be placed in the Public

-

Document Room.

1259

301

7 911020 D{

1

.

Northeast Nuclear Energy Company

2

No reply to this letter is required; however, if you should have any questions

concerning this inspection, we will be pleased to discuss them with you.

Sincerely.

-

<t

Eld n J. Brunner, Chief

Re ctor Operations and Nuclear

S'upport Branch

Enclosure:

Office of Inspection and Enforcement Combined Inspection

Report Number 50-245/79-17; 50-336/79-18

cc w/ enc 1:

J. F. Opeka, Station Superintendent

D. G. Diedrick, Manager of Quality Assurance

J. R. Himmelwright, Licensing Safeguards Engineer

A. Z. Roisman, Natural Resources Defense Council (Without Report)

1259