Forwards IE Insp Rept 50-423/79-06 on 790710-13.No Noncompliance Noted
ML19256E108
Person / Time
Site: Millstone Dominion icon.png
Issue date: 09/12/1979
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Counsil W
NORTHEAST NUCLEAR ENERGY CO.
Shared Package
ML19256E109 List:
References
NUDOCS 7910290054
Download: ML19256E108 (2)


See also: IR 05000423/1979006

Text

Y&

.,

UNITED STATES

p naco

o

NUCLEAR REGULATORY COMMISSION

$ g.} ) ,( /

R EGION 1

y

g

.g

631 PARK AVENUE

}

C

KING OF PRutSI A, PENNSYLVANIA 19404

sw j

+....

SEP 12 59

Docket No. 50-423

Northeast Nuclear Energy Company

ATTH: Mr. W. G. Counsil

Vice President - Nuclear

Engineering and Operations

P. O. Box 270

Hartford, Connecticut 06101

Gentlemen:

Subject:

Inspection 50-423/79-06

This refers'to the inspection conducted by Mr. A. Varela of this office on

Aly 10-13,1979 at the Millstone Nuclear Power Station, Unit 3, at Waterford,

Connecticut of activities authorized by NRC License No. CPPR-ll3 and to the

discussions of our findings held by Mr. Varela with Mr. S. Toth of your

staff at the conclusion of the inspection.

Areas examined during this inspection are described in the Office of

Inspection and Enforcement Inspection Report which is enclosed with this

letter. Within these areas, the inspection consisted of selective examinations

of procedures and representative records, interviews with personnel, and

observations by the inspector.

Within the scope of this inspection, no items of noncompliance were observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a c'ny of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If

this report contains any information that you (or your contractor) believe

to be proprietary, it is necessary that you make a written application

within 20 days to this office to withhold such information from public

disclosure. Any such application must be accompanied by an affidavit

executed by the owner of the infonnation, which identifies the document or

part sought to be withheld, and which contains a statement of reasons which

addresses with specificity the items which will be considered by the Commission

as listed in subaaragraph (b)(4) of Section 2.790.

The information sought

to be withheld s1all be incorporated as far as possible into a separate

part of the affidavit.

If we do not hear from you in this regard within

the specified period, the report will be placed in the Public Document

Room.

,977

324

,

7 910290 OM f

.

Northeast Nuclear Energy Company

2

No reply to this letter is required; however, should you have any questions

concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

4

-

Robert T. Car son, Chief

Reactor Construction and Engineering

Support Branch

Enclosure: Office of Inspection and Enforcement Inspection

Report Number 50-423/79-06

cc w/ enc 1:

K. W. Gray, Construction Quality Assurai.ce Lead

H. R. Nims, Director of Nuclear Projects

J. F. Opeka, Station Superintendent